Hwy 73 resurfacing project

St. Louis County

Project completed

Hwy 73 project map
Hwy 73 project map. Click for larger PDF version.

 

Work phasing plan

Summary of work

  • Mile marker 18 to 25 (south of Cromwell) resurfacing
  • Mile marker 31.3 to 33.6 (north of Cromwell) resurfacing
  • Mile marker 43.1 to 43.7 (Floodwood) resurfacing and accessibility improvements
  • Mile marker 48 to 69.6 (north of Floodwood) resurfacing

Project Improvements

In Floodwood

  • New curb and gutter and sidewalk
  • Upgraded curb ramps on Highway 2
  • 2-inch mill and 2-inch overlay
  • North of Floodwood River, road width reduced and parking removed
  • Minor city utility work—sanitary sewer

Rural segments

  • Six culvert replacements
  • North of Floodwood — Rural segment 1.5-inch mill and 3-inch overlay including shoulders

Past meetings

A public meeting was held May 11, 2017