Project begins in full force June 4

Reconstruct eastbound Highway 10 road surface from Clear Lake to Big Lake, and improve the access at Highway 10 and County Rd 23/Sherburne Ave with a new Reduced Conflict Intersection (RCI) in Becker. Work begins in full force June 4, 2018. Tentative schedule, traffic plans on both directions of Highway 10.

Crews clear trees May 21-24

Eastbound Highway 10: Motorists to encounter periodic lane or shoulder closures along eastbound Highway 10 from Clear Lake to Big Lake, as crews clear trees and brush, during daylight hours, Monday, May 21 to Thursday, May 24. For current road conditions on Hwy 10, check 511mn.org

Memorial Day Weekend May 25-27: Highway 10 will be open from Clear Lake to Big Lake. However, eastbound Highway 10 in Elk River will be reduced to a single-lane of traffic 24/7.

Future traffic impacts

Plan for delays on both directions of Hwy 10

Highway 10 to be reduced to a single lane of traffic between Clear Lake and Big Lake. Expect reduced speeds, lane shifts and use of narrow temporary lanes June-October 2018.

Highway 10 Clear Lake to Big Lake - 2018 construction project map
Plan for lane closures on Hwy 10 from Clear Lake to Big Lake from June 4 to Oct. 19, 2018.

Schedule at a glance

Information is tentative and dependent upon contractor, schedules, materials and weather.

2018 Hwy 10 Traffic Impacts Work
May 21-24 Lane or shoulder closures Remove trees and brush
June 4 to mid-July Clear Lake to Big Lake: Segments of single lane traffic on both directions Install temp lanes/crossovers, prep work
Mid-July to mid-Sept. Clear Lake to Big Lake: Single lane head-to-head traffic 24/7 on westbound side; temp signal at Hwy 25 in Becker TRAFFIC PLAN MAP

Reconstruct eastbound road surface

Mid-Sept. to Oct. 19 Clear Lake to Big Lake: Segments of single lane closures on both directions Remove temp lanes, crossovers and complete other work
Mid-Sept. to Oct. 19 Becker: Single lane closures on both directions, access detour for up to two weeks at CR 23/Sherburne Ave Reconstruct intersection (RCI) at Hwy 10 and CR 23/Sherburne Ave

Local access

Access to businesses and residences to be maintained, follow signs.

Sign-up for project updates

Live in the area? You may want to subscribe to project email updates for the Hwy 10 Clear Lake to Big Lake project. We'll send you the latest news about traffic and detour changes.

About this 2018 project

Reconstruct eastbound Highway 10 road surface from Clear Lake to Big Lake, and improve the access at Highway 10 and County Rd 23/Sherburne Ave with a new Reduced Conflict Intersection (RCI) in Becker.

Summary of work