About the project
Update
Work is complete. Crews completed the final repairs of Hwy 56 and opened the road Monday morning, Nov. 2. Hwy 56 had 236 repairs on the concrete highway between West Concord and Hwy 14, which required a detour during the work. I-35 was completed earlier in the season and I-90 was done last month. Thank you for your patience and safe driving.
Summary of work
A MnDOT contractor did concrete pavement repair on small stretches of I-35 (southbound 4 miles north of Faribault), I-90 (westbound passing lane between Stewartville and Dexter) and Hwy 56 (West Concord to Hwy 14).
- Work on I-35 began September 24
- Work on I-90 began September 28
- Work on Hwy 56 began September 30