Culvert replacement

Traffic impacts

Map showing culvert replacement locations on Hwy 40
  • A two stage detour will be required for this project
  • Stage 1 detour will start on May 17, 2021 and end on June 22, 2021
  • Stage 2 detour will start on June 23, 2021 and end on August 20, 2021

About this project

  • Replacement of three culverts with box culverts