Summary of MnDOT work

  • Resurface one mile of Hwy 19 in Marshall from the junction of Hwy 19/23 to just west of 280th Avenue
  • Resurface 17 miles of Hwy 59 from north of Lyon County Road 33 to south of Yellow Medicine County Road 3

Traffic impacts

  • Project will be completed under traffic. No detour is required.
  • Lane and/or shoulder closures will be necessary.
  • Expect short delays and flagging operations during shoulder/lane closures.

Project updates

Sept. 18, 2020

  • Resurfacing operations on US 59 and Hwy 19 are complete.
  • Guardrail and shoulder work are complete.
  • Rumble strip installation is complete.
  • Fog seal is complete.
  • Work suspended until Sept. 30 to allow fog seal coat to cure.