About this project
BNSF is planning to replace the tracks on Hwy 68, just south of the Hwy 68 and Hwy 59 junction in Marshall. In conjunction, MnDOT is planning to repair catch basins and install drain tile in the area.
Summary of work
- Replace railroad tracks (BNSF)
- Repair catch basins (MnDOT)
- Install drain tile (MnDOT)
Traffic impacts
- A detour is required for this project (map to be posted soon)
Project benefits
- Improve drainage
- Enhance driver safety
Contractor
- BNSF Railway (tracks)
- To be determined (drainage repair)
Cost
- Approximately $200,000 (MnDOT)
Contact
- Diana Heston
Construction supervisor
320-979-3327