Project Number | Route | Letting Date | Posted Date | Comments End | Document Links | Comments & Responses |
---|---|---|---|---|---|---|
SP 6005-69 | US 2 | 2/27/2015 | 1/27/2025 | 2/18/2025 | 6005-69 Documents | |
SP 6007-15 | MN 32 | 11/20/2026 | 1/27/2025 | 2/18/2025 | 6007-15 Documents | |
SP 2908-31 | MN 200 | 7/6/2025 | 1/27/2025 | 2/18/2025 | 2908-31 Documents | |
SP 6806-31 | MN 89 | 1/23/2026 | 1/27/2025 | 2/18/2025 | 6806-31 Documents | |
SP 1505-25 | MN 200 | 11/24/2024 | 1/27/2025 | 2/18/2025 | 1505-25 Documents | |
SP 2909-18 | MN 87 | 11/22/2024 | 1/27/2025 | 2/18/2025 | 2909-18 Documents | |
SP 0416-55 | MN 197 | 10/24/2025 | 1/27/2025 | 2/18/2025 | 0416-55 Documents | |
SP 0410-51 | US 71 | 12/5/2025 | 1/27/2025 | 2/18/2025 | 0410-51 Documents | |
SP 0410-53 | US 71 | 2/26/2027 | 10/23/2024 | 11/14/2024 | 0410-53 Documents | 0410-53 Comments Response |