Current

Update

  • Now open: Maple Grove Pkwy over new Hwy 610 between Co Rd 81 and 99th Ave.
  • Hwy 610 is expected to open to traffic between I-94 and Co Rd 81 by mid-December

Through late-November

  • As work continues on the BNSF Railroad tunnels along the south side of Hennepin Co Rd 81 in Maple Grove, watch for trucks and other construction traffic moving in and out of the work zone.
  • The new tunnels will carry traffic in each direction on the  new Hwy 610 alignment over the railroad tracks.

Future

Mid-December 2016

  • Hwy 610 is expected to open to traffic between Hennepin Co Rd 81/Elm Creek Blvd and I-94
  • Demolition of 101st Ave. North will be scheduled in mid- to late-December following the opening of Hwy 610. A half mile segment of 101st Ave. N. was closed between I-94 and Fernbrook Ln.

 

About this project

Summary of work

  • Realign and extend Hwy 610 from its current location at Hennepin Co Rd 81 and Elm Creek Blvd to I-94 in Maple Grove
  • Construct Hwy 610 bridge over Fernbrook Ln.
  • Construct interchange at Hwy 610 and Maple Grove Pkwy.
  • Close and remove a half mile segment of 101st Ave. North, between I-94 and Fernbrook Ln.
  • Extend 105th Ave. west from Holly Ln. across I-94 to a new intersection with 101st Ave.

This project was built using a process called Design-Build.

Read about construction staging