Minnesota Department of Transportation

511 Travel Info

Highway 3 Safety Improvements

Empire Township, Farmington

About this project

Highway 3 safety improvements project area map in Empire Township and Farmington

Hwy 3 project area map.

Click map for larger PDF version.

Crews will convert the intersection of Hwy 3 and 170th St. into a single lane roundabout; convert bypass lanes to dedicated left turn lanes at 200th St., 197th St. and Chesterfield Way; and construct a new left turn lane at 209th St. These improvements are planned to increase safety and mobility on Hwy 3. The roundabout at Hwy 3 and 170th St. will provide a safer intersection by reducing turning conflicts and slowing speeds. Conversion of the bypass lanes to dedicated left turn lanes are also expected to improve safety on the roadway.

Summary of work

  • Add a roundabout at 170th St.
  • Construct left turn lanes at 200th St., 202nd St./Chesterfield Way, 197th St. and 209th ┬áSt.

Traffic impacts

Upcoming

Information about upcoming traffic impacts will be posted as details become available. Motorists can expect a full closure of Hwy 3 between Co. Rd. 64 and Co. Rd. 46 for approximately 2 months. Note: All businesses and residences will remain accessible throughout the project however, it may not be your normal route.