A more than eight-mile section of I-35 between the city of Harris and the Chisago/Pine County line underwent a concrete road resurfacing project. The work included concrete pavement work, drainage updates and safety improvements. This section of I-35 was first paved in 1969. The road received pavement overlay treatments in 1987 and 2008.

Summary of work

  • Resurfaced concrete pavement
  • Removed and replaced cable median barriers
  • Added rumble strips
  • Updated drainage
  • Replaced lighting at Rush City interchange