Studies, Plans and Future Highway Improvement Projects
Find out about studies, plans and future construction for state highways.
Festival Season
Sometimes roads will close due to festivals and parades. List of festivals and parades.
Want to get involved?
Let your voice be heard by getting involved in meetings and hearings.
Find Information about city and county roads
Projects Completed in 2011
Almost everyone is glad when we get another project done, so we will keep this running list of completed projects as the construction season winds down. Some of the benefits from these projects include:
- A smoother ride
- Extended pavement life
- Increased safety and reduced highway fatalities and serious injuries
- Better accessibility for all Minnesotans
- Improved connections between communities
- Infrastructure preservation
This page was last updated March 20, 2012.
Hwy 1
Hwy 1 west of Clearwater County line in Red Lake
Description: Bridge painting and landscape work
Construction Dates: April - May 2011
Hwy 1 Oslo to Warren
Description: Resurface road and replace culverts
Construction Dates: June - July 2011
Hwy 2
Hwy 2, Hwy 169 in Itasca County
Description: install flashing lights
Construction Dates: May - June 2011
Hwy 2 east of Crookston
Description: Resurface road
Construction Dates: May - June 2011
Hwy 2 in Crookston
Description: Construct curb ramps, install signals
Construction Dates: July - mid Oct. 31
Hwy 4
Hwy 4 south of Sleepy Eye
Description: Replace bridge over the Little Cottonwood River
Construction Dates: May - late Oct.
Hwy 5
Hwy 5 in St. Paul
Description: Repair bridge railing
Construction Dates: Oct. 19-mid November
Hwy 6
Hwy 6 Crosby
Description: Resurface roadway from Hwy 210 to County Road 11
Construction Dates: Oct. 17- end of October
Hwy 7
Hwy 7 at Blake Rd. and Aquila Ave.
Description: CenterPoint maintenance work
Construction Dates: July 31-late August 2011
Hwy 7 at Baker Rd and Lake Street Exit in Minnetonka
Description: Replace lighting
Construction Dates: May – July 2011
Hwy 7 from County Road 101 to I-494 in Minnetonka
Description: Resurfacing
Construction Dates: June 2011
Hwy 7 north of Ortonville
Description: Emergency road repair
Construction Dates: Aug. 29-Sept. 14
Hwy 7, Hwy 55 and I-394 in Hennepin County
Description: Install fiber optics and traffic cameras for congestion management
Construction Dates: March – October 2011
Hwy 8
Hwy 8 between I-35 in Forest Lake and Karmel Avenue in Chisago City
Description: Resurfacing
Construction Dates: June 2011
Hwy 9
Hwy 9 in Morris
Description: Resurface road, repair culverts
Construction Dates: May 12 –- late June 2011
Hwy 9 south of Borup
Description: Replace culvert
Construction Dates: June 2011
Hwy 9 from Hwy 23 to 1st Ave North in New London
Description: Resurface roadway, install accessible pedestrian ramps and sidewalk
Construction Dates: August - October
Hwy 9 Norman/Clay county line to Hwy 10
Description: Resurface, replace three bridges, signal installation at Hwy 10 with intersection improvements
Construction Dates: May 31 –- mid-December
Hwy 10
Hwy 10 Wadena
Description: Resurface, install turn lanes, pedestrian access improvements
Construction Dates: Sept. 19-late Oct. 2011
Hwy 10 Clear Lake to Big Lake
Description: Install temporary bypass lanes for 2012 pavement replacement
Construction Dates: Oct 3 to Nov. 2011
Hwy 10 Frazee to Detroit Lakes
Description: Resurface road
Construction Dates: June 2011
Hwy 10 Hawley to Detroit Lakes
Description: Resurface road
Construction Dates: May 11 – mid-June 2011
Hwy 10 west of Glyndon
Description: Install weigh-in-motion system
Construction Dates: Early September 2011
Hwy 10 St. Cloud to Clear Lake
Description: Landscaping on WB lanes
Construction Dates: June 2010-May 2011
Hwy 10 Big Lake to Elk River
Description: Landscape
Construction Dates: August 2010-May 2011
Hwy 10 at Foley Blvd/County Road 11 in Coon Rapids
Description: Add dual right turn lanes at westbound Hwy 10 exit to south Foley Blvd, revise signal, remove free right to southbound Foley Blvd from the westbound Hwy 10 exit
Construction Dates: August–September 2011
Hwy 10 north of Hwy 115 to east end of Little Falls bypass
Description: Resurface roadway, construct/extend turn lanes, install or repair culverts
Construction Dates: May–September 2011.
Description: Widen and resurface Hwy 10; realign and reconstruct Hwy 25 to the RR tracks; replace traffic signal system/lighting
Construction Dates: May-October 2011
Hwy 11
Hwy 11
Hwy 11, Clementson
Description: Construct bridge deck, turf and erosion control
Construction Dates: May-October
Traffic Impacts: No delays, minor cleanup
Hwy 12
Hwy 12 from 6th St. E. to 24th St. in Willmar
Description: Resurface roadway
Construction Dates: May 2011
Hwy 12 from Hwy 59 to Benson
Description: Sealcoat shoulder
Construction Dates: Late-August – late-September
Hwy 13
Hwy 13 near I-494 in Eagan
Description: Resurfacing, guardrail and drainage updates
Construction Dates: May – June 2011
Hwy 13 at I-35E in Lilydale
Description: New signal system, turn lane and sidewalk
Construction Dates: Sept. 6 – Oct. 10
Hwy 14
Hwy 14 Winona County
Description: Install pedestrian ramps for accessibility
Dates: May - June 2011
Hwy 14 from Hwy 52 to Marion Rd
Description: Resurfacing, improve intersection and traffic signals, improve intersections, bike path addition
Construction Dates: May - end of Sept.
Hwy 16
Hwy 16 Rushford to Houston
Description: Resurface.
Dates: Oct. 5-early Nov.
Hwy 19
Hwy 19 New Prague by Hwy 13 north
Description: Resurface road
Construction Dates: October 2011
Hwy 19 in Marshall
Description: Construct sidewalk and trail, install accessible pedestrian signals from Bruce St to jct of Hwy 23
Construction Dates: Oct. 3 - early Nov.
Hwy 19 west junction of
Hwy 71/Hwy 67 near Redwood Falls
Description: Restore historic retaining wall and guardrail
Construction Dates: May through early October
Hwy 20
Hwy 20 from Hwy 50 to Hwy 19 in Cannon Falls and Douglas Township
Description: Replace signs
Construction Dates: August 2011
Hwy 22
Hwy 22 Gaylord to Hwy 212
Description: Resurface road
Construction Dates: September - October 2011
Hwy 23
Hwy 23 and Hwy 301 in St. Cloud
Description: Resurfacing of roads
Construction Dates: Oct. 17 – early-November
Hwy 23 near New London
Description: Seal coat roadway
Construction Dates: August
Hwy 23 and Hwy 70 in Stearns and Kanabec
Description: Seal coat roadway
Construction Dates: June 15 – mid-July 2011
Hwy 23 east junction of Hwy 212 to Hwy 7 in Clara City
Description: Repair concrete pavement
Construction Dates: June – late-October
Hwy 23 Spicer
Description: Refurbish light poles
Construction Dates: June – November
Hwy 25
Hwy 25 east of Monticello
Description: Widen intersections, install turn lanes
Construction Dates: June – early November
Hwy 25 in Foley
Description: Utility work
Construction Dates: Aug. 15 – late-August
Hwy 25 Belle Plaine
Description: Reconstruct bridge railing
Construction Dates: April-May 2011
Hwy 27
Hwy 27 in Little Falls
Description: Repair railroad track
Construction Dates: June 2011
Hwy 27 Hwy 27 Herman to Hoffman
Description: Resurface road
Construction Dates: September – early November
Hwy 28
Hwy 28 west state line through Beardsley
Description: Resurface road
Construction Dates: June 20 – early August
Hwy 28 North of Swanville
Description: Replace Swan River bridge
Construction Dates: July-mid October.
Hwy 29
Hwy 29 Wadena to Hwy 210
Description: Resurface road, replace culverts
Construction Dates: Aug. 1– Mid-October
Hwy 29 from Hwy 210 to Carlos
Description: Sealcoat shoulder
Construction Dates: Aug. 29 – late September
Hwy 29 McKay Ave to 3rd Ave in Alexandria
Description: Resurface road, restripe roadway to add northbound lane
Construction Dates: September – Mid-October
Hwy 30
Hwy 30 Watonwan River west of Darfur
Description: Replace bridge
Construction Dates: July-mid-October 2011
Hwy 30 Westbrook and Hwy 62 by Fulda
Description: Resurface road
Construction Dates: Late September to early October 2011
Hwy 30 near Blooming Prairie
Description: Railroad crossing
Construction Dates: September 2011
Hwy 30 Amboy to Mapleton
Description: Restore pavement
Construction Dates: June – mid-October 2011
Hwy 30 in Darfur
Description: Install pedestrian ramps
Construction Dates: September
Hwy 30 in Steele and Waseca counties, Hwy 13 to Twp Rd 50
Description: Resurface
Dates: Sept. 19 – late-October 2011
Hwy 32
Hwy 32 from Hwy 10 to Hwy 34
Description: Replace guardrail
Construction Dates: Sept. 19 – mid-October 2011
Hwy 34
Hwy 34 Park Rapids to Akeley, Hwy 226 to Dorset
Description: Resurface, install turn lanes, replace culverts
Construction Dates: June 2011 – September 2011
I-35
I-35 near Cloquet and Sandstone
Description: Re-deck bridges over I-35 at Hwy 33 and Hwy 23
I-35 at County Road 2 and Hwy 61 in Forest Lake
Description: Bridge and interchange reconstruction, rebuild Broadway Avenue
Construction Dates: April – October 2011
I-35 South of Duluth
Description: Reconstruction
Construction Dates: 2011
I-35 over Willow River in Pine County
Description: Repair bridges
Construction Dates: June – Sept.
I-35E
I-35E at County Road 14 in Lino Lakes
Description: Reconstruct I-35E/ County Road 14 interchange in Anoka County. This project advanced through American Recovery and Reinvestment Act funding.
Construction Dates: April 15, 2010 – June 30, 2011
I-35E at Hwy 13 in Lilydale
Description: New signal system, turn lane and sidewalk
Construction Dates: Sept. 6 – Oct. 10, 2011
I-35E from Lone Oak Road in Eagan to County Road 5 in St. Paul
Description: Pavement resurfacing, guardrail repairs, signal upgrades and other improvements
Construction Dates: Aug. 18 – November 2011
I-35W
I-35W Ramp in Minneapolis
Description: Rehabilitate storm tunnel
Construction Dates: Dec. 5 -Feb. 2012
I-35W south of Minneapolis
Description: Construct lanes for bus rapid transit
Construction Dates: June 4, 2007 – July 1, 2011
I-35W from Burnsville Pkwy to I-494 in Burnsville and Richfield
Description: Replace signs
Construction Dates: October – November 2011
Traffic Impacts: Occasional shoulder or lane closures
I-35W from 106th Street to 94th Street in Bloomington
Description: Replace lighting
Construction Dates: June – September 2011
I-35W at County Road D in Roseville
Description: Rebuild traffic signal
Construction Dates: September – November 2011
I-35W Burnsville
Description: Additional MnPASS lanes will open in 2011
Construction Dates: Construction completed Oct. 28, 2011
I-35W
Description: Construct lanes for bus rapid transit
Construction Dates: June 4, 2007 – June 1, 2011
Hwy 36
Hwy 36 at Commerce Street and Hamline Ave in Roseville
Description: Rebuild traffic signal
Construction Dates: Spring 2011
Hwy 36 and Rice Street Intersection
Description: Rice Street will be widened, the Rice Street bridge will be replaced and the interchange will be reconstructed
Construction Dates: July 2010 – November 2011
Hwy 37
Hwy 37 Penobscott Creek near Hibbing
Description: Replace bridge
Construction Dates: June 2010 – June 2011
Hwy 41
Hwy 41 at 4th Street in Chaska
Description: Rebuild traffic signal
Construction Dates: May – June 2011
Hwy 43
Hwy 43 Rushford to I-90
Description: Resurface
Construction Dates: May – July 2011
Hwy 43 Fillmore County
Description: Install pedestrian ramps for accessibility
Dates: 2012
Hwy 43 Winona
Description: Monitor bridge
Dates: Oct. 26-27
Hwy 44
Hwy 44 Spring Grove to Caledonia
Description: Resurface, culvert replacement.
Dates: May – October 2011
Hwy 47
Hwy 47 north of Bradford at 317th Avenue
Description: Repair frost-damaged pavement
Construction Dates: Oct. 3 – mid-October
Hwy 50
Hwy 50 from Hwy 3 to Hwy 61
Description: Micro-surfacing
Construction Dates: May – June 2011
Hwy 51
Hwy 51 from Pierce Butler Route to Como Ave in St. Paul
Description: Concrete pavement and drainage repair
Construction Dates: September – December 2011
Traffic Impacts: Lane and shoulder closures
Hwy 52
Hwy 52 from Belvedere Street in St. Paul to 80th Street in Inver Grove Heights
Description: Bridge rehabilitation, cable median barrier and other roadway improvements
Construction Dates: April – Aug. 12, 2011
Hwy 52 south of I-494 in Inver Grove Heights
Description: Resurfacing, ADA upgrades and drainage improvements
Construction Dates: Aug. 2011 – Feb 2012
Hwy 52 Olmsted County, 65th St NW to Pine Island
Description: Install cable median barrier
Dates: May – early-October
Hwy 53
Hwy 53 southbound ramps in Duluth
Description: Resurfacing ramp to I-535 and Blatnik Bridge
Construction Dates: Aug. 2011
Hwy 55
Hwy 55 and Mendota Bridge
Description: Resurfacing bridge deck
Construction Dates: August 2011
Hwy 55 Paynesville to east of Hwy 4
Description: Resurface road, shoulders
Construction Dates: August 2011
Hwy 55 Elbow Lake to Grant/Douglas county line
Description: Seal roadway surface
Construction Dates: Aug. 10 – early-September 2011
Hwy 55, I-394, Hwy 7 – Hennepin County
Description: Install fiber optics and traffic cameras for congestion management
Construction Dates: March – October 2011
Hwy 55 and County Rd. 101 in Medina and Plymouth
Description: Repair the traffic signal wiring
Construction Dates: October 15-16
Hwy 58
Hwy 58 in Zumbrota
Description: Storm sewer inspection, cleaning
Construction Dates: Oct. 10-late Oct.
Hwy 59
Hwy 59 Sand Lake to Prairie Lake
Description: Construct outlet
Construction Dates: April 11 – mid-May 2011
Hwy 59 north of Lyon CR 33 to Yellow Medicine CR 3
Description: Resurface roadway
Construction Dates: June – August 2011
Hwy 59: South of Clarkfield to Lyon CR 3
Description: Widen shoulders and line culverts
Dates: June 2011 – late-Fall
Hwy 59 south of Clarkfield
Description: Widen shoulders and line culverts
Construction Dates: June
Hwy 60
Hwy 60 near Wabasha
Description: Replace bridge and approach road
Dates: June – September 2011
Hwy 61
Hwy 61 Split Rock River to Chapins Curve south of Beaver Bay
Description: Reconstruct roadway and replace bridge, four miles
Construction Dates: April 2010 – late-September 2011
Hwy 61 in St. Paul - Burns Avenue Overlook
Description: Extensive restoration of the historic Burns Avenue Overlook
Construction Dates: August 2009 – spring 2011
Hwy 61 near Grand Portage
Description: Construct turn lanes
Construction Dates: June 2011
Hwy 61 Onion River area north of Tofte
Description: Reconstruct roadway and replace bridge
Construction Dates: April 2009 – May 2011
Hwy 61 Wabasha to Lake City
Description: Repair slope due to floods
Construction Dates: June 2011
Hwy 61 at Minnehaha Ave in St. Paul
Description: Rebuild traffic signal
Construction Dates: April – October 2011
Hwy 61 Gilbert Creek in Lake City
Description: Replace bridge
Dates: April – September 2011
Hwy 61 in Winona
Description: Bridge painting
Dates: Oct. 12 – late-October
Hwy 62
Hwy 62 – Fulda to Windom
Description: Repair pavement
Construction Dates: September 2011
Hwy 63
Hwy 63 – 6th St intersection in Stewartville
Description: Improve intersection safety, modify traffic signals
Construction Dates: September – October 2011
Hwy 64
Hwy 64 south junction to north junction of Hwy 87
Description: Resurface
Construction Dates: September 2011
Hwy 65
Hwy 65 near Silverdale in Koochiching County
Description: Replace bridge
Construction Dates: July 2007 – mid-August 2011
Hwy 65 and Hwy 73 Aitkin County
Description: Install rumble strips
Construction Dates: May – June 2011
Hwy 65
in Mora
Description: Replace road signs
Construction Dates: August – September 2011
Hwy 65 Mora Lake to Hwy 27 in Woodland
Description: Road repairs, landscape
Construction Dates: July 2010 – June 2011
Hwy 65 in Fridley
Description: Emergency railroad crossing replacement
Construction Dates: Oct. 28-31
Hwy 67
Hwy 67—Hwy 23 to Yellow Medicine River Bridge
Description: Resurface road
Hwy 68
Hwy 68 New Ulm to Mankato
Description: Seal coating
Construction Dates: Aug. 2011
Hwy 70
Hwy 70 – Hwy 107 to Hwy 361
Description: Resurface pavement
Construction Dates: September – November
Hwy 71
Hwy 71 in Belgrade
Description: Replace drainage system from Owens Street to Hwy 55
Construction Dates: Mid-October – mid-November
Hwy 71 in Sauk Centre
Description: Install traffic signal
Construction Dates: May – June 2011
Hwy 71 Northome to Margie
Description: Resurface, replace culvert
Construction Dates: May – June 2011
Hwy 71 in Koochiching County
Description: 28-mile long resurfacing project
Construction Dates: July 28 – mid-October
Hwy 71 – south of Bemidji
Description: Construct new bridge over Hwy 2, expand Hwy 71 from two to four lanes, add turn lanes
Construction Dates: Mid-June – late October
Impacts: No traffic impacts, traffic is using the old bridge
Hwy 72
Hwy 72 Waskish to Hwy 11
Description: Resurface road, replace culverts
Construction Dates: Aug. 1 – Sept. 30, 2011
Hwy 74
Hwy 74 near Weaver
Description: Culvert replacement
Construction Dates: August 2011
Hwy 74 from Crookston to Warren
Description: Repair shoulders
Construction Dates: October 24-29
Hwy 75
Hwy 75/8th St S at 7th Avenue S in Moorhead
Description: Replace signal
Construction Dates: Aug. 1 – mid-September
Hwy 75 at Clay CR 12 (60th Ave South)
Description: Construct roundabout
Construction Dates: July 5 – Sept. 12, 2011
Hwy 75 bypass at Crookston
Description: Railroad crossing upgrade
Construction Dates: Aug. 1 to Sept. 16, 2011
Hwy 75 Stephen to Donaldson
Description: Resurface road
Construction Dates: Aug. 24 – Sept. 9
Hwy 75 Climax to Crookston
Description: Resurface road, install turn lanes, replace culverts
Construction Dates: Aug. 1 – Sept. 16
Hwy 76
Hwy 76 Houston County, Hwy 44 to Hwy 16
Description: Resurface, culvert replacements.
Dates: May – September 2011
Hwy 76 Houston and Winona counties, Hwy 16 to I-90
Description: Resurface.
Dates: Sept. 19 – early-November
Hwy 77
Hwy 77/Old Shakopee Road in Bloomington
Description: Bridge deck rehabilitation
Construction Dates: August – September 2011
Hwy 78
Hwy 78 Battle Lake to I-94
Description: Seal roadway surface
Construction Dates: Aug. 10 – early-September 2011
Hwy 83
Hwy 83 from Hwy 30 to Hwy 22
Description: Restore pavement, resurface road
Construction Dates: Aug. 15 – mid-October
Hwy 89
Hwy 89 Grygla to eight miles west of Fourtown
Description: Resurface
Construction Dates: Summer 2011
I-90
Hwy I-90 over Mississippi River
Description: Bridge maintenance
Construction Dates: August 2011
I-90 bridge near Nodine
Description: Bridge deck repairs
Construction Dates: August 2011
Hwy I-90 in Austin
Description: Storm sewer inspections and cleaning
Construction Dates: Sept. 14 – late-October
I-90 Hwy 63 to Olmsted CR 19
Description: Resurface WB lanes
Dates: Aug. through Sept.
I-90 Winona County, Hwy 43 to Hwy 76
Description: Resurface EB lanes
Dates: May – September 2011
I-94
I-94 and Hwy 10
Description: Replace road signs on Hwy 10 from St. Cloud to Little Falls and at Hwy 15 in Benton County and on I-94 from Hwy 15 in St. Cloud to the Wright/Hennepin County Line
Construction Dates: October – December
I-94 Monticello to St. Cloud
Description: Xcel to install CAPX2020 utility lines along I-94.
Construction Dates: August – December 2011
I-94 frontage road from Lowry Ave Bridge to 1st Ave Bridge in Minneapolis
Description: Resurface frontage road
Construction Dates: Oct. 3 – end of October
I-94 from 49th Ave in Minneapolis to Shingle Creek Pkwy in Brooklyn Center
Description: Paint bridges
Construction Dates: May – August 2011
I-94 at Shingle Creek Pkwy in Brooklyn Park
Description: Replace traffic lights at the Shingle Creek Pkwy ramps to/from I-94
Construction Dates: May – June 2011
I-94—34th St. South in Moorhead
Description: Realign interchange and street corridor
Construction Dates: September 2008 – September 2011
I-94 at St. Joseph
Description: Install lighting
Construction Dates: May 2011
I-94 in Monticello
Description: Paint overpasses, landscape
Construction Dates: July 2009 – May 2011
I-94 Stearns and Wright counties
Description: Upgrade guardrail
Construction Dates: June 2011
I-94 WB Barnesville to Downer exit
Description: Resurface roadway
Construction Dates: May 2 – Aug. 26, 2011
I-94 eastbound from northbound Hwy 61 to White Bear Avenue in St. Paul
Description: Construct eastbound auxiliary lane, update ramp metering
Construction Dates: Sept. 10 – mid-October, 2011
I-94 in Rogers
Description: Paint overpasses, landscape
Construction Dates: April 2010 – September 2011
I-94 in Albertville
Description: Install interchange safety improvements
Construction Dates: May 9 - early June 2011
I-94 Lake Iverson rest area
Description: Permanently close rest area, demolish structures. Rest area permanently closed.
Construction Dates: Sept. 12 – late September
I-94 EB Rothsay to Hwy 59
Description: Resurface eastbound lanes
Construction Dates: Early September – mid-October
I-94/Hwy 101 in Rogers
Description: Construct overpass from I-94 westbound to Hwy 101 northbound over South Diamond Lake Road in Rogers. Update existing guardrail and drainage systems from the Crow River to 1.6 miles east of Hwy 101; Also Lighting System Replacement at I-94 and Hwy 101 in Rogers, and resurfacing from Rogers to Maple Grove
Construction Dates: April 2010 – September 2011
I-94 east of Albany to Collegeville
Description: Resurface roadway
Construction Dates: Sept.13 - mid November
Hwy 95
Hwy 95 in Cambridge
Description: Install traffic signal system
Construction Dates: August – September 27, 2011
Hwy 95 in Princeton
Description: Paint bridges, landscape
Construction Dates: June 2010
Hwy 95 in Forest Lake
Description: in Forest Lake and built new 11th Avenue (County Road 83) bridge over I-35 which is now open to traffic. Construction will resume Spring 2011. Landscaping will take place in 2011 but the project will not be active over the winter months.
Construction Dates: Dec. 1, 2009 – Spring 2011
Hwy 95 in Forest Lake
Description: Reconstruct Broadway Avenue (Washington County Road 2) bridge. Reconstruction of County Road 2 between 19th Street and 7th Street. Also reconstruction of County Road 2 bridge over I-35. Ramps at I-35 and County Road 2 will remain open to traffic. Temporary ramps will be located south of the intersection at County Road 83. For more information visit the project website (www.broadwayaveforestlake.info)
Construction Dates: May 2011 – October 2011
Hwy 100
Hwy 100 from W. 50th Street/Vernon Ave in St. Louis Park to Hwy 55
Description: Replace signs
Construction Dates: May – June 2011
Hwy 100 from Brooklyn Blvd/County Road 152 to I-694
Description: Replace lighting
Construction Dates: April – June 2011
Hwy 100 from Brooklyn Blvd/County Road 152 to eastbound I-94 in Brooklyn Center
Description: Resurfacing
Construction Dates: July – September 2011
Hwy 101
Hwy 101 Shakopee
Description: Reconstruct historic Holmes Street bridge (currently a pedestrian bridge)
Construction Dates: Oct. 1, 2009 – June 3, 2011
Hwy 101 from Bramble Drive to just south of Pioneer Trail in Chanhassen
Description: Reconstruct highway
Construction Dates: Oct. 3 – Oct. 17
Hwy 107
Hwy 107 Braham to Hwy 23 west of Brook Park
Description: Resurface road, shoulders, repair or replace culverts
Construction Dates: May – early September
Hwy 108
Hwy 108 near Dent
Description: Flood prevention, raise roadbed
Construction Dates: Oct. 10-14
Hwy 108 Ottertail to Henning
Description: Seal roadway surface
Construction Dates: Aug. 10 – early-September 2011
Hwy 112
Hwy 112 – South of LeSueur
Description: Culvert replacement
Construction Dates: August 2011
Hwy 113
Hwy 113 Mahnomen CR 4 to Hwy 71
Description: Seal roadway surface
Construction Dates: Aug. 10 – early September 2011
Hwy 120
Hwy 120 at Century College entrance in White Bear Lake
Description: Rebuild signal
Construction Dates: August – Sept 2011
Hwy 149
Hwy 149 from north of Mendota Heights Road to Smith Ave in Mendota Heights and West St. Paul
Description: Seal road
Construction Dates: August 2011
Hwy 169
Hwy 169 in New Hope
Description: Noise wall installation
Construction Dates: Mid-September - Early October
Hwy 169 between Scott County Rd 18 and Pioneer Trail
Description: Restriping, modifications at the Hwy 169/I-494 interchange for temporary flood relief
Construction Dates: Spring 2011
Hwy 169 Triangle in Brooklyn Park and Osseo
Description: Reconstruction of Hwy 169 triangle
Construction Dates: Through August 2011
Hwy 169 from 63rd Ave. to 77th Ave. in New Hope and Brooklyn Park
Description: Install cable median barrier
Construction Dates: November – December 2011
Traffic Impacts: Overnight lane closures
Hwy 169 and Hwy 610
Description: New Hwy 610 alignment Hwy 169 in Brooklyn Park and County Road 81 in Maple Grove
Construction Dates: Through August 2011
Hwy 169 – Bridge repairs in Mankato
Description: Repair bridge deck over Minnesota River Bridge
Construction Dates: July 26-27
Hwy 169 north of Milaca
Description: Install a Rural Intersection Collision Avoidance System
Construction Dates: June 2011
Hwy 169 to Hwy 10 in Elk River
Description: Resurface bridge deck and upgrade railings
Construction Dates: June 2011
Hwy 169 at 173rd Street in Sandcreek Township
Description: Revise intersection, close access, reconstruct backage road. The project is being led by Scott County. See project website.
Construction Dates: September - November 5, 2011
Hwy 169 Garrison Concourse at Mille Lacs Lake
Description: Restore historical masonry wall
Construction Dates: October 2010-November 2011
Hwy 210
Hwy 210 Battle Lake to Highway 29
Description: Seal roadway surface
Construction Dates: Aug. 10 – early September 2011
Hwy 210 I-94 to Otter Tail CR 82 (Pebble Lake Rd)
Description: Resurface roadway
Construction Dates: Aug. 2011
Hwy 210 in Carlton County
Description: Replace box culvert
Construction Dates: Oct. 2011
Hwy 212 near Hector to Hwy 22 near Glencoe
Description: Grade, resurface, construct turn lanes
Construction Dates: May-Nov
Hwy 218
Hwy 218 Mower County, IA/MN state line to I-90
Description: Resurface
Construction Dates: August to September 2011
Hwy 227
Hwy 227 seven miles east of Sebeka
Description: Replace Cat River bridge
Construction Dates: July-August 2011
Hwy 241
Hwy 241—I-94 ramp at St. Michael
Description: Install traffic signal system
Construction Dates: Aug. 25-late September
Hwy 246
Hwy 246 Northfield to Nerstrand
Description: Resurface
Dates: Aug. 25- early Oct.
Hwy 247
Hwy 247 Wabasha County
Description: Install pedestrian ramps for accessibility
Construction Dates: June-July 2011
Hwy 248
Hwy 248 Rollingstone to Hwy 61
Description: Resurface
Dates: Aug-Sept 2011
Hwy 258
Hwy 258
Description: Repairs to bridge
Dates: Oct. 31-Nov. 4
Hwy 270
Hwy 270 east of Hills
Description: Replace bridge over Mud Creek
Construction Dates: Aug. 22-mid October 2011
Hwy 371 Baxter to Nisswa
Description: Resurface roadway and make safety improvements
Construction dates: Summer 2011-end of September
I-394
I-394, Hwy 7 and Hwy 55 – Hennepin County
Description: Install fiber optics and traffic cameras for congestion management
Construction Dates: March – October 2011
I-494
I-494 at Nicollet Ave and 2nd Ave Bridges in Bloomington and Richfield
Description: Resurface and update bridges
Construction Dates: August – October 2011
Hwy 610
Hwy 610 in Maple Grove/Brooklyn Park
Description: Construct three miles of Hwy 610 from County Road 81 to Hwy 169 in Maple Grove and Brooklyn Park
Construction Dates: September 2009 – Fall 2011
Hwy 952
Hwy 952 Robert St. Bridge
Description: Maintenance work
Construction Dates: August 2011