Minnesota Department of Transportation

511 Travel Info

Hwy 610

Maple Grove (Elm Creek Boulevard to I-94)

Traffic impacts

Hwy 610 project map
Click map for larger PDF version.

Current

Full closure

  • Southbound Fernbrook Lane (County Road 121) closed between County Road 81 and 99th Avenue. Northbound Fernbrook Lane will remain open. The road will reopen by 6 a.m. Thursday, May 21.
  • 101st Avenue N closed between Maple Grove Parkway and Fernbrook Lane. 101st Ave N will remain open from Maple Grove Parkway to the Maple Grove Yard Waste entrance. 101st Avenue will reopen by 6 a.m. Thursday, May 21, 2015.

Motorists should follow the signed detour on Maple Grove Parkway and 99th Avenue during both closures.

Future

Lane closures

  • I-94 traffic will be maintained during most of the project however there will be occasional non-rush hour lane closures.
  • Fernbrook Lane will have short term closures for utility work and to set bridge beams in 2015
  • Maple Grove Parkway closed spring of 2016 to fall of 2016
  • County Road 81 will have occasional temporary non-rush hour  lane closures

About this project

Summary of work

  • Realign and extend Hwy 610 from its current location at Hennepin County Road 81 and Elm Creek Boulevard to I-94 in Maple Grove.
  • Construct Hwy 610 bridge over Fernbrook Lane.
  • Construct interchange at Hwy 610 and Maple Grove Parkway.
  • Close and remove a half mile segment of 101st Avenue North, between I-94 and Fernbrook Lane.
  • Extend 105th Ave west from Holly Lane across I-94 to a new intersection with 101st Avenue.

This project will be built using a process called Design-Build.

Read about construction staging

Cost