Install 10 miles of high-tension safety cable median barrier on Hwy 10 between Benton Co. Rd. 40, also known as the Halfway Crossing, west of Rice and 66th St. west of Sauk Rapids. Motorists will encounter lane closures, lane shifts and reduced speeds. Expect multiple crews and equipment within the work zone.Google map of project location.
When complete in late June, the $1.3 million safety improvement project will prevent crossover collisions with on-coming motorists, which will save lives. If you have any questions, contact Michelle Hoff, MnDOT construction project manager, at michelle.t.hoff@state.mn.us.
PLAN AHEAD: One-lane traffic begins July 11
About this 2022 project
Summary of work
Hwy 10 between Co. Rd. 33 and 66th St NE. Select map for pdf
Replace a box bridge under Hwy 10 three miles west of Sauk Rapids between the Benton Co. Rd. 33 interchange and 66th St. NE.
Future impacts
Late June to early July
Install temporary crossovers in the median and prepare work areas.
Expect periodic lane and shoulder closures
July 11 to late August
Close and replace one side of box bridge at a time
Install 10 miles of high-tension safety cable median barrier on Hwy 10 between Benton Co. Rd. 40, also known as the Halfway Crossing, west of Rice and 66th St. west of Sauk Rapids. Motorists will encounter lane closures, lane shifts and reduced speeds. Expect multiple crews and equipment within the work zone.Google map of project location.
When complete in late June, the $1.3 million safety improvement project will prevent crossover collisions with on-coming motorists, which will save lives. If you have any questions, contact Michelle Hoff, MnDOT construction project manager, at michelle.t.hoff@state.mn.us.