Hwy 30 repaving

Ellendale

About this project

Update

Construction started July 26, 2021 and was completed Sept. 17, 2021.

Summary of work

    Hwy 30 Ellendale Project map
    Hwy 30 project area
  • Hwy 30 repaved from 0.28 miles west of Ellendale to 1 mile east of Steele Co. Rd. 45
  • Culvert work at three locations east of Steele Co. Rd. 45 and at Steele Co. Rd. 14 just north of Hwy 30
  • Realignment of 8th Ave. E intersection and Hwy 30
  • ADA improvements

Traffic impacts

None - project is complete.