About this project

Map of Hwy 271 resurfacing work from the junction of Hwy 19 to the border of MN with SD excluding the town of Hendricks.

Summary of work

MnDOT work

  • Resurface Hwy 271 from the junction of Hwy 19 to the Minnesota / South Dakota border, excluding the town of Hendricks.

 

Traffic impacts

  • Work on Hwy 271 south of Hendricks is being done using a detour (follow the blue route on the map above).
  • Detour effective Sept. 13 - Oct. 2.
  • Thru traffic will use the detour route of Hwy 19, Hwy 75 and CR 17.
  • Work on Hwy 271 north of Hendricks will be done under traffic using temporary lane closures, a flagging operation and pilot car through the work zone.
  • Motorists can expect minor delays.

Project updates

Friday, September 24, 2021

  • Work continued this week on the roadway south of Hendricks.
  • Stabilized full depth reclamation work continued and should finish up Sat., Sept. 25, weather permitting; this is a process where the old asphalt/base material is pulverized, stabilized, compacted and recycled into a new durable base material.
  • Micro-milling (removal of the old pavement surface) is tentatively scheduled to begin Wed., Sept. 29 on the roadway north of Hendricks - this will be done under traffic with flaggers and a pilot car.
  • The first lift of asphalt paving is tentatively scheduled to begin Thu., Sept. 30, for the portion of roadway south of Hendricks.