About this project

  • Replace the bridge over the Cottonwood River south of Sanborn. The existing bridge was built in 1931 and is near the end of its useful life.
  • The new bridge will be wider with 12-foot driving lanes and 10-foot shoulders.
  • Minor work will take place on the approaches to improve drainage on the bridge, including reshaping the ditches and stream stabilization.
  • New guardrail will be installed.

Traffic impacts

  • The US 71 Cottonwood River crossing will remain closed during construction (shown in red on map); please use the detour route (blue line on map) which follows Brown CR 21 & 2, and Hwy 14.
  • The city bridge river crossing (shown in orange on map) will also be closed and detoured during the project.

Map showing US 71 bridge location in Sanborn and detour route

Project updates

Friday, October 22, 2021

  • This week, crews graded and paved the asphalt shoulders.
  • Work scheduled to be completed by end of day:
    • Install topsoil, guardrails, and a temporary center line stripe.
  • Detour is scheduled to be removed by end of day.
  • Work remaining for next week (under traffic):
    • Install permanent striping, rumble strips and erosion control

An aerial view of the new Sanborn bridge on US 71.