All traffic impacts are tentative and weather dependent.

Current

Road closures

10 p.m. Fri, April 30 through 5 a.m. Mon, May 3

  • WB I-94/I-694 is closed between Hwy 100 and Brooklyn Blvd.
    • Detours: 
      • NB I-94/SB Hwy 252: NB Hwy 252 to WB Hwy 610 to SB Hwy 169
      • WB I-94/694: SB Hwy 100, WB I-394 to NB Hwy 169
    • Loop from Shingle Creek Pkwy to WB intestate and ramp from SB Hwy 252 to WB I-94/I-694 closed
    • Ramp from WB I-94/I-694 to Brooklyn Blvd. closed. All other ramps at Brooklyn Blvd. open.

Ramp closures

Mon, April 12 through mid-May
  • The following ramps are closed:
    • Brooklyn Blvd. to EB I-94/I-694
    • WB I-94/I-694 to Brooklyn Blvd.
      • Detour: WB I-94/I-694 to Co. Rd. 81/Bottineau Blvd. to EB I-94/I-694

Upcoming

Information about upcoming traffic impacts will be provided as details become available. There will be four weekend closures on I-94/I-694 from Brooklyn Blvd. to Dupont Ave.

About this project

Crews will repair and resurface both directions of I-94/I-694 in Brooklyn Center. The project also includes drainage improvements and work to bring pedestrian/bicycle crossings along the project area up to Americans with Disability Act standards.

Summary of work

  • Resurface the interstate
  • Concrete pavement repairs
  • Drainage improvements
  • Upgrade pedestrian/bicycle crossings to ADA standards