Upcoming traffic impacts

- Construction resumes April 2025!
- Work will start on Highway 59, north of Fifth Avenue NE up to Eighth Avenue NW in Stage 2B
- Automated traffic signal will be installed on both sides of the work zone to direct traffic one lane at a time. Your patience is important!
- There will be a thru-traffic detour set up for truck traffic and those who are seeking an alternate route around construction
- Early/mid-April: Bridge crews will be completing work at the bridge over the Pelican River downtown. Expect parking and sidewalk restrictions on the east side of the bridge.
- In May, work will resume on Highway 108 east, too!
Construction schedule
Construction will be completed in phases, starting in April 2024 through Fall 2025. All work and schedules are weather dependent.
Upcoming stages and work:
- Starting in April Bridge work downtown, parking/sidewalk restrictions
- Starting in April Stage 2B: Hwy 59, Fifth Ave NE to Eighth Ave NW
- Starting in May Stage 4A: Hwy 108 east, 2 1/2 Street to 4th Street
- View all project staging maps. Subject to change.