I-90 resurfacing, bridge replacement

Nodine to Dakota

About this project

Summary of work

Improvements were made on I-90 between Nodine and Dakota in Winona County. Construction started May 4, 2026. This project is considered substantially complete. You'll see brief lane closures into December 2026 as cleanup and final work is completed, but the lane closures will only be in place while that work is being done.

The following improvements were made on I-90:

I-90 Nodine Hills map
I-90 project map
  • Repaved 5 miles of westbound and 4.7 miles of eastbound I-90.
  • Replaced the westbound I-90 bridge over Winona County Road 101.
  • Replaced approach panels and bridge barrier guardrail connections on the westbound I-90 bridge over southbound Hwy 61.
  • Improved safety by providing a slight banking of the right lane of northbound I-90 approaching the bridge over southbound Hwy 61.
  • Installed new guardrail on the eastbound and westbound lanes and improve drainage.
  • Installed a reinforcement and a synthetic liner to reduce sinkhole risks associated with Karst geology.
  • Cleaned and reestablished rock catchment areas.