Minnesota Department of Transportation

511 Travel Info

Hwy 60

Madison Lake, Elysian, Waterville

Orange barrels on a highway

Weekly construction updates

September 30-October 8
  • Mainline Highway 60 bituminous paving has been completed.  Various entrances remain to be paved with this work being completed by the week of October 8.
  • Aggregated shoulder on Highway 60 is being progressed toward the City of Waterville.  This work requires trucks hauling material as well as heavy equipment working on the placement.  The traveling local public should continue to exercise caution while on Highway 60.
  • Pavement markings (i.e., striping) is planned for the week of October 8.
  • Sign installation is planned for the week of October 8.
  • The installation of rumble strips is planned to begin on Friday, October 1.
  • Turf establishment and erosion/sediment control work activities will continue, and general clean-up of both Phase 1 & Phase 2 work areas will commence shortly.
  • It is anticipated that the project will be substantially complete and opened to the traveling public by the week of October 22.
September 21-28
  • Bituminous paving is planned to begin at Le Sueur CR 11, in the City of Elysian, on Friday, September 7th and progressing toward the City of Waterville.  The traveling public should expect the potential of short-term delays while the bituminous material is being delivered, placed, compacted, and cooled.  Typically, these delays are not more than 20 – 30 minutes.
  • *Patching and Milling work on Spruce St. in the City of Madison Lake will occur on 9/23.  The bituminous overlay work will occur early next week as part of an earlier agreement.  Short-term delay should be expect by the traveling public.
  • The traveling public should also be aware of the traffic control barriers at crossing intersections of Hwy 60 and not move them in order to drive on or across Hwy 60.  The construction and/or MnDOT staff will move them as soon as possible.
  • In the event that the traveling public needs to have access via Hwy 60 during paving, accommodations will be made but the public is encouraged to not drive around barriers or amongst construction vehicles due to safety and roadway surface concerns.
  • Grading and cutting of the full-depth reclamation of the existing roadway will continue from East Elysian Lake Rd to the City of Waterville.
  • Excavation and embankment work will continue on the west side of the City of Waterville in the area of Hwy 60 and Reed St.
  • Excavation and embankment work will continue on the west side of the City of Waterville in the area of Hwy 60 and Reed St.
September 14-21
  • Bituminous paving is planned to begin at Le Sueur CR 11, in the City of Elysian, on Friday, September 7th  and progressing toward the City of Waterville.  The traveling public should expect the potential of short-term delays while the bituminous material is being delivered, placed, compacted, and cooled.  Typically, these delays are not more than 20 – 30 minutes.
  • The traveling public should also be aware of the traffic control barriers at crossing intersections of Highway 60 and not move them in order to drive on or across Highway 60.  The construction and/or MnDOT staff will move them as soon as possible.
  • In the event that the traveling public needs to have access via Highway 60 during paving, accommodations will be made but the public is encouraged to not drive around barriers or amongst construction vehicles due to safety and roadway surface concerns.
  • Work of installing entrance culverts will continue with minimal impacts to the traveling public.
  • Grading and cutting of the full-depth reclamation of the existing roadway will continue from East Elysian Lake Road to the City of Waterville.
  • Excavation and embankment work will continue on the west side of the City of Waterville in the area of Highway 60 and Reed St.
September 10-17
  • Bituminous paving is planned to begin at Le Sueur County Road 11 in the City of Elysian on Friday, Sept. 7th  and progressing toward the City of Waterville.  The traveling public should expect the potential of short-term delays while the bituminous material is being delivered, placed, compacted, and cooled.  Typically, these delays are not more than 20 – 30 minutes.
  • The traveling public should also be aware of the traffic control barriers at crossing intersections of Highway 60 and not move them in order to drive on or across Highway 60.  The construction and/or MnDOT staff will move them as soon as possible.
  • In the event that the traveling public needs to have access via Highway 60 during paving, accommodations will be made but the public is encouraged to not drive around barriers or amongst construction vehicles due to safety and roadway surface concerns.
  • Work of installing entrance culverts will continue with minimal impacts to the traveling public.
  • Grading and cutting of the full-depth reclamation of the existing roadway will continue from East Elysian Lake Road to the City of Waterville
  • Excavation and embankment work will continue on the west side of the City of Waterville in the area of Highway 60 and Reed St.
August 16-23
  • The detour for Phase 2 is fully implemented as originally planned (Hwy 13 to Le Sueur CR 12 to Le Sueur 11 to the City of Elysian).
  • Centerline culvert will be replaced and installed at various locations from the eastside of the City of Elysian to the City of Waterville (with primary focus in the area of 440th Ave.).  Access may be limited for relatively short periods of time and considerations are being made for at least one side of the culvert work
  • Excavation and embankment work for the widening sections around CR 3(East Elysian Lake Rd.), CR 6 and CR 62.
  • Local residents east of County Road 3 to the City of Waterville on Hwy 60 should expect short-term delays as various construction activities progress.  Every effort will be made to provide access in as reasonable amount of time as possible.  MnDOT thanks you for your understanding in advance.
  • Phase 1 clean-up is wrapping up.  The completion of the reconstruction work associated with 516th is scheduled for this week, including turf establishment.
August 9-16
  • The detour for Phase 2 is fully implemented as originally planned (Hwy 13 to Le Sueur County Road 12 to Le Sueur 11 to the City of Elysian).
  • Centerline culvert will be replaced and installed at various locations from the eastside of the City of Elysian to the City of Waterville (with primary focus in the area of 440th Ave.).  Access may be limited for relatively short periods of time and considerations are being made for at least one side of the culvert work
  • Excavation and embankment work for the widening sections around CR 3(East Elysian Lake Rd.), CR 6 and CR 62.
  • Local residents east of County Road 3 to the City of Waterville on Highway 60 should expect short-term delays as various construction activities progress.  Every effort will be made to provide access in as reasonable amount of time as possible. MnDOT thanks you for your understanding in advance.
August 2-9
  • The detour for Phase 2 is fully implemented as originally planned (Hwy 13 to Le Sueur County Road 12 to Le Sueur 11 to the City of Elysian).
  • Hwy 60 was opened from the intersection of Hwy 14 & Hwy 60 to County Road 11 in the City of Elysian this morning. Please note that Hwy 60 east of the intersection with County Road 11 is closed to through traffic.  Local traffic should expect periodic delays as construction progressing toward the City of Waterville.
  • Centerline culvert will be replaced and installed at various locations from the eastside of the City of Elysian to the City of Waterville.  Access may be limited for relatively short periods of time and considerations are being made for at least one side of the culvert work
  • Excavation and embankment work for the widening sections around County Road 6 and County Road 62.
  • Local residents east of County Road 3 to the City of Waterville on Hwy 60 should expect short-term delays as various construction activities progress.  Every effort will be made to provide access in as reasonable amount of time as possible.  MnDOT thanks you for your understanding in advance.
July 26-August 2
  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups.  This work is currently progressing.
  • Residents, businesses, and pedestrians of Madison Lake will have limited access from 7th St. to 1st St. this week and into next week as a variety of construction work is being performed which includes sidewalk, turf establishment, signage and pavement marking.
  • Aggregate shouldering and final striping and clean-up are intended to be completed by the end of the week of July 30.
  • Bituminous paving will continue the week of July 26 on Hwy 60 between the Cities of Madison Lake and Elysian with the focus being between East Elysian Lake Road and County Road 11 in the City of Elysian.  It is anticipated, weather depending, that the final lift will be placed and completed from west of Madison Lake through the intersection of County Road 11, in the City of Elysian by next week.  Along with the paving work, aggregate shouldering material, striping & signage etc. is on schedule to be completed by the end of the week of July 30.
  • A modified short-term detour was implemented on Monday, July 12.  This detour will send Hwy 60 traffic on the Phase 2 portion involving the use of Hwy 13 in the City of Waterville onto Le Sueur County Road 12 to County Road 11 in the City of Elysian, then east on Hwy 60 to Waseca County Road 3 (East Elysian Lake Rd.).  Hwy 60 east of Waseca CR 3 will be closed to through traffic for the remainder of the project.  It is anticipated that traffic would be detoured west on Hwy 60 at the intersection of County Road 11 in the City of Elysian the end of the week of August 2 and Hwy 60 would be closed to through traffic from the intersection of County Road 11 to the City of Waterville.
  • The traveling public should be aware of the new stop condition at the intersection of Le Sueur Co. Rds. 11 and 12 for the upcoming detour. There are currently Portable Changeable Message Boards stationed on County Road 12, either side of the intersection with County Road 11, which state that there will be an All-Way Stop.  The department would appreciate your help in making this information available to as many people as possible.
  • Work began on Monday, July 12 on Hwy 60 east of Waseca County Road 3 (East Elysian Lake Road).  This work includes milling of the existing bituminous pavement and the replacement of the various centerline culverts. The residents on the section of Hwy 60 between the City of Elysian and the City of Waterville should anticipate potential delays in access to their homes and businesses.  The contracting forces will be working as quickly as possible to complete their work and to reestablish access.
  • Centerline Culvert work from County Road 62 to Waterville.
  • Excavation and embankment work for the widening sections around County Road 6.
  • Local residents east of County Road 3 to the City of Waterville on Hwy 60 should expect short-term delays as various construction activities progress.  Every effort will be made to provide access in as reasonable amount of time as possible.  MnDOT thanks you for your understanding in advance.
July 19-26, 2021
  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups. This work is currently progressing.
  • Residents, businesses, and pedestrians of Madison Lake will have limited access from 7th St. to 1st St. this week and into next week as a variety of construction work is being performed which includes sidewalk, turf establishment, signage and pavement marking.
  • *Residents and visitors to the Madison Lake Paddle Fish celebration, this weekend, should be aware of construction activities, equipment on Walnut St. (Highway 60) and use the pedestrian access road crossing located at Main St. and 4th St. Also, please be aware that the sidewalk has not been completed so proceed with caution when walking on Walnut St.  Please do not move barricades or go into areas where barriers have been installed.
  • Aggregate shouldering and final striping and clean-up are intended to be completed by the end of the week of July 30.
  • Edge drains are currently being installed at various locations in order to aid in stabilizing the grade prior to bituminous paving. This work in planned to be completed by July 21.
  • Bituminous paving will continue the week of July 26 on Highway 60 between the Cities of Madison Lake and Elysian with the focus being between East Elysian Lake Rd and CR 11 in the City of Elysian.  It is anticipated, weather depending, that the final lift will be placed and completed from west of Madison Lake through the intersection of County Road 11, in the City of Elysian by next week.  Along with the paving work, aggregate shouldering material, striping & signage etc. is on schedule to be completed by the end of the week of July 30.
  • A modified short-term detour was implemented on Monday, July 12.  This detour will send Highway 60 traffic on the Phase 2 portion involving the use of Highway 13 in the City of Waterville onto Le Sueur County Road 12 to County Road 11 in the City of Elysian, then east on Highway 60 to Waseca County Road 3 (East Elysian Lake Rd.).  Highway 60 east of Waseca County Road 3 will be closed to through traffic for the remainder of the project.  It is anticipated that traffic would be detoured west on Highway 60 at the intersection of County Road 11 in the City of Elysian by the end of the week of July 19 and Highway 60 would be closed to through traffic from the intersection of County Road 11 to the City of Waterville.
  • The traveling public should be aware of the new stop condition at the intersection of Le Sueur Co. Roads 11 and 12 for the upcoming detour. There are currently Portable Changeable Message Boards stationed on County Road 12, either side of the intersection with County Road 11, which state that there will be an All-Way Stop.  The department would appreciate your help in making this information available to as many people as possible.
  • Work began on Monday, July 12 on Highway 60 east of Waseca County Road 3 (East Elysian Lake Road).  This work includes milling of the existing bituminous pavement and the replacement of the various centerline culverts. The residents on the section of Highway 60 between the City of Elysian and the City of Waterville should anticipate potential delays in access to their homes and businesses.  The contracting forces will be working as quickly as possible to complete their work and to reestablish access.
July 6-16, 2021
  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups.  This work is currently progressing.
  • Residents, businesses, and pedestrians of Madison Lake will have limited access from 7th St. to 1st St. this week and into next week as the final lift of bituminous paving is placed.
  • The final course of bituminous paving will occur in the City of Madison Lake this week.
  • Aggregate shouldering and final striping and clean-up are intended to be completed by the end of the week of July 19.
  • Road/pedestrian crossing locations
  • Bituminous paving continues on Hwy 60 between the Cities of Madison Lake and Elysian for the first lift.  It is anticipated, weather depending, that the final lift will be placed and completed from west of Madison Lake through the intersection of County Road 11, in the City of Elysian by next week.  Along with the paving work, aggregate shouldering material, striping & signage etc. is on schedule to be completed by the end of the week of July 19.
  • A modified short-term detour was implemented on Monday, July 12.  This detour will send Highway 60 traffic on the Phase 2 portion involving the use of Hwy 13 in the City of Waterville onto Le Sueur County Road 12 to County Road 11 in the City of Elysian, then east on Highway 60 to Waseca County Road 3 (East Elysian Lake Rd.).  Highway 60 east of Waseca County Road 3 will be closed to through traffic for the remainder of the project.  It is anticipated that traffic would be detoured west on Highway 60 at the intersection of County Road 11 in the City of Elysian by the end of the week of July 19 and Highway 60 would be closed to through traffic from the intersection of County Road 11 to the City of Waterville.
  • The traveling public should be aware of the new stop condition at the intersection of Le Sueur Co. Rds. 11 and 12 for the upcoming detour. There are currently Portable Changeable Message Boards stationed on CR 12, either side of the intersection with CR 11, which state that there will be an All-Way Stop.  The department would appreciate your help in making this information available to as many people as possible.
  • Work began on Monday, July 12 on Highway 60 east of Waseca County Road 3 (East Elysian Lake Road).  This work includes milling of the existing bituminous pavement and the replacement of the various centerline culverts. The residents on the section of Highway 60 between the City of Elysian and the City of Waterville should anticipate potential delays in access to their homes and businesses.  The contracting forces will be working as quickly as possible to complete their work and to reestablish access.
July 6-16, 2021
  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups.  This work is currently progressing.
  • Residents, businesses, and pedestrians of Madison Lake will have limited access from 7th St. to 1st St. this week and into next week as the final lift of bituminous paving is placed.
  • Bituminous paving will occur at the various side-street approaches in the City of Madison Lake this week.
  • The work of adjusting and raising the manhole/inlets on Highway 60 (Walnut Street) in the City of Madison Lake will begin by the end of this week.
  • Bituminous paving continues on Highway 60 between the Cities of Madison Lake and Elysian for the first lift.  It is anticipated, weather depending, that the final lift will be placed and completed from west of Madison Lake through the intersection of County Road 11, in the City of Elysian by next week.  Along with the paving work, aggregate shouldering material, striping & signage etc. is on schedule to be completed by the July 16.
  • A modified short-term detour is planned to begin on Monday, July 12.  This detour will send Highway 60 traffic on the Phase 2 portion involving the use of Highway 13 in the City of Waterville onto Le Sueur County Road 12 to County Road 11 in the City of Elysian, then east on Highway 60 to Waseca County Road 3 (East Elysian Lake Rd.).  Highway 60 east of Waseca County Road 3 will be closed to through traffic for the remainder of the project.  It is anticipated that traffic would be detoured west on Highway 60 at the intersection of County Road 11 in the City of Elysian beginning July 16 and Highway 60 would be closed to through traffic from the intersection of CR 11 to the City of Waterville.
  • The traveling public should be aware of the new stop condition at the intersection of Le Sueur Co. Rds. 11 and 12 for the upcoming detour. There are currently portable changeable message boards stationed on County Road 12, either side of the intersection with County Road 11, which state that there will be an All-Way Stop. 
June 28-July 6, 2021
  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups.  This work is currently progressing.
  • Driveway culverts throughout the project with minimal disruptions.
  • Residents, businesses, and pedestrians of Madison Lake will have limited access from 7th St. to 1st St. on Thursday and Friday this week as the second lift of bituminous paving is placed.
  • Concrete sideway and curb & gutter work will continue in the City of Madison Lake.
  • Bituminous Paving is currently completed from the intersection of Hwy 14/Hwy 60 to Park Road in the City of Madison Lake.
  • Road/pedestrian crossing locations
  • Phase 2 detour modification (July 9-16, 2021)
  • *Residents along Hwy 60 from the City of Madison Lake to the City of Elysian should expect short-term delays with no access during the bituminous paving (aka asphalt) process, which is anticipated to begin on June 11.  The bituminous pavement will be placed in 2 or 3 separate lifts, depending on the location. Once the paver and all rollers have completed the placement and compaction work for a particular lift, it will be 20 to 30 minutes before passenger vehicles may drive on it.  It will be 60 minutes before commercial vehicles will be allowed on the paved surface. The public is strongly encouraged to not use Hwy 60 during the paving operations out of concern for the safety and damage for both the new roadway surface and the traveling public’s vehicles and persons.
  • Primary focus of bituminous paving will in the City of Madison Lake. The first lift of bituminous pavement was placed last week and the second is planned for later this week. Access will be limited as the 3 lifts of bituminous pavement is placed.  We will do our best to provide access with as minimal a disruption as possible.  The paving work in the City of Madison Lake should be completed within the next week.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  The department would like to remind the local traveling public that while Hwy 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Hwy 60 and allow time for using a different route to your destination. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along Hwy 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

June 21-28, 2021
  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups. This work is currently progressing.
  • Driveway culverts throughout the project with minimal disruptions.
  • Residents and businesses of Madison Lake will have limited access from 7th St. to 1st St.
  • Pedestrian and traffic access for the City of Madison Lake will be at Main St. and 4th St.
  • Bituminous paving is currently being progressed from the intersection of Hwy 14/Hwy 60 by the end of this week and progressing toward the City of Madison Lake, ending at Park Road.
  • Excavation work at the intersection of Hwy 60 and Le Sueur CSAH 13. CSAH 13 will have no access to Hwy 60 for approximately 1 week.
  • Excavation work at the intersection of CSAH 61 and Hwy 60.
  • Excavation at the intersection of Hwy 60 and CR 11 in the City of Elysian.  *Signs to be moved back to the original location at NE 2nd St.
  • Milling and pavement removal on Hwy 60 in the City of Elysian to east of the intersection of N. 1st St (CR 11). The public should expect delays and limited to no access during this process. This work should take approximately 2 weeks.
  • *Residents along Hwy 60 from Hwy 14 to the City of Elysian should expect short-term delays with no access during the bituminous paving (aka asphalt) process, which is anticipated to begin on June 11. The bituminous pavement will be placed in 2 or 3 separate lifts, depending on the location. Once the paver and all rollers have completed the placement and compaction work for a particular lift, it will be 20 to 30 minutes before passenger vehicles may drive on it.  It will be 60 minutes before commercial vehicles will be allowed on the paved surface. The public is strongly encouraged to not use Hwy 60 during the paving operations out of concern for the safety and damage for both the new roadway surface and the traveling public’s vehicles and persons.
  • Primary focus of Bituminous Paving will in the City of Madison Lake.  Access will be limited as the 3 lifts of bituminous pavement is placed.  We will do our best to provide access with as minimal a disruption as possible.  The paving work in the City of Madison Lake should be completed within the next week.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  The department would like to remind the local traveling public that while Hwy 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Hwy 60 and allow time for using a different route to your destination. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along Hwy 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

June 14-21, 2021
  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups. This work is currently progressing.
  • Driveway culverts throughout the project with minimal disruptions.
  • Concrete curb & gutter work in the City of Madison Lake from 4th St. to the approximate eastside of town.
  • Residents and businesses of Madison Lake will have limited access from 7th St. to 1st St.
  • Pedestrian and traffic access for the City of Madison Lake will be at Main St. and 4th St.
  • Bituminous paving is currently being progressed from the intersection of Highway 14/Highway 60 by the end of this week and progressing toward the City of Madison Lake, ending at Park Road.
  • Excavation work at the intersection of Hwy 60 and Le Sueur CSAH 13.  CSAH 13 will have no access to Hwy 60 for approximately 1 week.
  • Excavation at the intersection of Hwy 60 and CR 11 in the City of Elysian.  *Signs to be moved back to the original location at NE 2nd St.
  • Milling and pavement removal on TH 60 in the City of Elysian to east of the intersection of N. 1st St (CR 11).  The public should expect delays and limited to no access during this process. This work should take approximately 2 weeks.
  • Road/pedestrian crossing locations
  • *Residents along Hwy 60 from Hwy 14 to the City of Elysian should expect short-term delays with no access during the bituminous paving (aka asphalt) process, which is anticipated to begin on June 11.  The bituminous pavement will be placed in 2 or 3 separate lifts, depending on the location. Once the paver and all rollers have completed the placement and compaction work for a particular lift, it will be 20 to 30 minutes before passenger vehicles may drive on it.  It will be 60 minutes before commercial vehicles will be allowed on the paved surface. The public is strongly encouraged to not use Hwy 60 during the paving operations out of concern for the safety and damage for both the new roadway surface and the traveling public’s vehicles and persons.  MnDOT and the contractor will work with individual property owners and specifically notifying the residents of Tomahawk Ct. and Nifty Home Prod. Inc. as to the best timing of the anticipated impact avoidance during the paving process.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  The Department would like to remind the local traveling public that while Hwy 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Hwy 60 and allow time for using a different route to your destination. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along TH 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

June 7-14, 2021

  • *The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups.  This work should begin within this week.
  • Centerline culvert from CSAH 61 to the City of Elysian.
  • Driveways culverts throughout the project. There will be minimal disruptions.
  • Grading work in the City of Madison Lake from 4th St. to the approximate eastside of town.
  • Residents and businesses of Madison Lake will have limited access from 7th St. to 1st St.
  • Pedestrian and traffic access, for the City of Madison Lake, will be at Main St. and 4th St.
  • Bituminous paving to begin at the intersection of Hwy 14/TH 60 by the end of this week and progressing toward the City of Madison Lake.
  • Road/pedestrian crossing locations
  • *Residents along Hwy 60 from Hwy 14 to the City of Elysian should expect short-term delays with no access during the bituminous paving (aka asphalt) process, which is anticipated to begin on June 11.  The bituminous pavement will be placed in 2 or 3 separate lifts, depending on the location. Once the paver and all rollers have completed the placement and compaction work for a particular lift, it will be 20 to 30 minutes before passenger vehicles may drive on it.  It will be 60 minutes before commercial vehicles will be allowed on the paved surface. The public is strongly encouraged to not use Hwy 60 during the paving operations out of concern for the safety and damage for both the new roadway surface and the traveling public’s vehicles and persons.  MnDOT and the contractor will work with individual property owners and specifically notifying the residents of Tomahawk Ct. and Nifty Home Prod. Inc. as to the best timing of the anticipated impact avoidance during the paving process.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  The Department would like to remind the local traveling public that while Hwy 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Hwy 60 and allow time for using a different route to your destination. 
The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along Hwy 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

May 31 - June 7, 2021
  • The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines and hooking up individual properties.  This work should begin within the next week.
  • Centerline culvert installation from CSAH 61 to the City of Elysian.
  • Driveway culvert installation throughout the Phase 1 portion of the project, this will mean short-term delays and lack of access.
  • Excavation and grading work being performed in the City of Madison Lake from 4th St. to approximately 500 feet east of 1st St.
  • City of Madison Lake resident and business access will be periodically interrupted from 7thSt. to east of 1st St.
  • City of Madison Lake pedestrian and vehicle access will be at Main St. and 4th St.
  • Excavation and grading work CSAH 13.
  • Road/pedestrian crossing locations
  • Residents along Hwy 60 from Hwy 14 to the City of Elysian should expect short-term delays with no access during the bituminous paving (aka asphalt) process, which is anticipated to begin on June 10.  The public is strongly encouraged to not use Hwy 60 during the paving operations out of concern for the safety and damage for both the new roadway surface and the traveling public’s vehicles and persons.  MnDOT and the contractor will work with individual property owners and specifically notifying the residents of Tomahawk Ct. and Nifty Home Prod. Inc. as to the best timing of the anticipated impact avoidance during the paving process.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  MnDOT would like to remind the local traveling public that while Hwy 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Hwy 60 and allow time for using a different route to your destination. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along Hwy 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

 

May 24-31, 2021
  • Centerline & box culvert installation from eastside of the City of Madison Lake to CR 48.
  • Driveway culvert/entrance work performed throughout the project, except minimal delays.
  • Excavation and grading work in the area of CSAH 61.
  • Excavation and grading work from 4th St. to the east end of the City of Madison Lake.
  • Concrete curb and gutter/sidewalk preparation from 7th St. to 4th St.
  • Milling and reclamation of the existing TH 60 road surface from the intersection of Hwy 14 & Hwy 60 to the City of Madison Lake.
  • Excavation and various grading activities in the area of CSAH 48.
  • The residents of the City of Madison Lake should be aware that there may be some limited electrical power outages as Xcel Energy begins the work of replacing the overhead lines with buried lines as well as during the individual property hook-ups. This work should begin within the next week.
  • Over the next 2 to 3 weeks there will be a focused effort to perform various utility and construction activities from 7th St. to 1st St. This will require several short term and longer-term interruptions to access to both businesses and residences.
  • Road/pedestrian crossing locations

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  The department would like to remind the local traveling public that while Hwy 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Hwy 60 and allow time for using a different route to your destination. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along Hwy 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

May 17-24, 2021
  • Centerline & Box Culvert installation from eastside of the City of Madison Lake to County Road 48.
  • Driveway culverts at various locations throughout the project. Expect some short-term delays.
  • Excavation and embankment work from CSAH 44 south to CSAH 44 north.
  • Utility work from 4th St. to eastside of the City of Madison Lake.
  • Excavation and embankment in the area of CSAH 48.
  • Residents and Business access will be limited from 7th St. to 1st St. in the City of Madison Lake.
  • Pedestrian and Vehicle traffic access at 4th St. in the City of Madison Lake.
  • Road/pedestrian crossing locations

The residents of the City of Madison Lake should be aware that over the next 2 to 3 weeks there will be a focused effort to perform various utility and construction activities from 7th St. to 1st St. This will require several short term and longer-term interruptions to access to both businesses and residences.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  The Department would like to remind the local traveling public that while Highway 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on TH 60 and allow time for using a different route to your destination. 
The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along TH 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along TH 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

 

May 11-18, 2021
  • Centerline culvert work from the intersection of Highway 14 & Highway 60 to Madison Lake.
  • Centerline culvert work from CSAH 14 to CR 11 (City of Elysian).
  • Driveway/entrance culvert throughout the project. Expect short-term delays.
  • Excavation and grading work from CSAH 44 South to CSAH 44 North.
  • City of Madison Lake utility work from 4th St. to eastside of city limits.
  • Excavation/embankment (sand & base material) placed from 7th St. to 4th St.
  • Excavation in the area of CSAH 48.
  • Residential/business access will be limited from 7th St. to 1st St.
  • Pedestrian and vehicle access will be available at 4th St.

The residents of the City of Madison Lake should be aware that over the next 2 to 3 weeks there will be a focused effort to perform various utility and construction activities from 7th St. to 1st St. This will require several short term and longer-term interruptions to access to both businesses and residences.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  MnDOT would like to remind the local traveling public that while Highway 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Highway 60 and allow time for using a different route to your destination. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along Highway 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

May 4-11, 2021
  • Centerline and entrance culvert work from the intersection of Highway 14 & Highway 60 to 222nd St.
  • Centerline and entrance culvert work from 241st Ave. to 221st St.
  • Geofoam installation from just north of 227th St. to Park Rd on Highway 60.
  • Centerline and entrance work various location east of the City of Madison Lake to just east of CSAH 61.
  • Excavation and grading work from CSAH 44 North and South.
  • Underground utility work in the City of Madison Lake from 7th St. to 3rd St.
  • Excavation work from 7th St. to 4th St.

The residents of the City of Madison Lake should be aware that over the next 2 to 3 weeks there will be a focused effort to perform various utility and construction activities from 7th St. to 1st St. This will require several short term and longer-term interruptions to access to both businesses and residences.

The public should be aware that as work progresses both in the City of Madison Lake and in the rural locations west and east of the city, that the condition of the roadway is subject to change from within the timeframe of a day.  MnDOT would like to remind the local traveling public that while Highway 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to assure completion in a timely manner.  Please plan on limiting your time on Highway 60 and allow time for using a different route to your destination. 

The various contracting forces, City of Madison Lake engineering staff and MnDOT have been appreciative of the understanding and patience of the residence who live along Highway 60. In particular, the people who live, work, shop, and worship in Madison Lake during this fast-paced construction process. While construction impacts everyone to a certain extent, the City of Madison Lake has experienced the brunt of the disruption caused by this needed work.  We are working as quickly as possible to provide a new efficient, safe, and cost-effective roadway and infrastructure.  Thus far, there has been limited delays due to weather or other uncontrollable events and we expect that the work is on schedule to be completed as originally intended. 

April 27-May 4, 2021
  • Centerline from the intersection of Highway 14 and Highway 60 to 222nd St.
  • Centerline and approach culvert removal and replacement from east of Madison Lake to 231st Ave.
    • *Note: centerline culvert work will necessitate the complete closure of Highway 60 to the traveling public for safety concerns at these locations.
  • Driveway culverts at various locations throughout project.  Minimal disruptions to be expected.
  • Excavation and grading work on Highway 60 in area of CSAH 44.
  • The removal of existing and installation of new utilities in the city of Madison Lake from 7th St. to 3rd St.
  • Embankment work to widen Highway 60 from east of Township Road 310 to east of County Road 189.

The public should be aware that as work progresses in the city of Madison Lake and in the rural locations west and east of the city, the condition of the roadway is subject to change from within the timeframe of a day.  The department would like to remind the local traveling public that while Highway 60 is accessible to local traffic, they should expect delays and closures with minimal advanced warning.  The nature of construction work requires flexibility and adjustment with work type and location to ensure completion in a timely manner.  Please plan on limiting your time on Highway 60 and allow time for using a different route to your destination.

April 19-26, 2021
  • Centerline and approach culvert removal and replacement on Highway 60 from 222nd St. to 7th St. in the City of Madison Lake.
  • Centerline and approach culvert work on Highway 60 from 251st Ave. to County Road 13.
  • Various driveway culverts will be worked on throughout the project.  There will be short-term traffic delays.
  • Excavation and embankment work at 222nd St.
  • Excavation and embankment work at County Road 44.
  • The City of Madison Lake work will generally be limited to a segment from 7th St. to 5th St. The residents of Madison Lake should be aware that construction traffic and activities will be present along all locations in the vicinity of Walnut Ave.
  • Resident and Business access will be limited from 7th St. to 3rd St.
  • The work associated with the City of Madison Lake will be conducted in two separate phases. Phase 1 will be from 7th St. to the area of 3rd St.  Once Phase 1 is completed, Phase 2 will begin and take off from the area of 3rd St. to approximately 500' east of 1st.
April 15-17, 2021
  • Begin removing of the pavement in Madison Lake (Walnut Ave.) from 7th to 3rd streets. This will be performed by a milling machine. This work will also include the removal of the curb and gutter.
  • Temporary water will be installed in Madison Lake.
  • Begin removing pavement over various pipe culverts and areas of intended widening in the rural areas outside of Madison Lake.  This work is intended to begin west of Madison Lake and gradually progress toward Elysian, at County Road 11 and the completion of Phase 1.
  • There will be excavation on the west shoulder of the existing Highway 60 beginning just south of 222nd St. and continuing for approximately 1,000 feet toward Madison Lake.