I-90 resurfacing

Austin to Dexter

About this project

I-90 project map
I-90 project map

I-90 will be resurfaced from Austin to Dexter. Work also includes improving exit and entrance ramps.

2025 work

Construction scheduled May 12 to late-August.

  • Resurface westbound I-90
    • 28th St. NE in Austin to 0.4 miles east of Hwy 16 near Dexter
  • Resurface and improve westbound I-90 exit and entrance ramps

Summer 2028-2029 work

  • Resurface eastbound I-90
    • 28th St. NE in Austin to 0.4 miles east of Hwy 16 near Dexter
  • Resurface and improve eastbound I-90 exit and entrance ramps
  • Remove and replace box culverts at Rose Creek

Traffic impacts

Traffic will remain on I-90 during construction. Vehicles will be detoured around closed ramps.

2025 ramp detour maps

2028 ramp detour maps are not yet available. The maps will be provided online and announced through the project email updates.