US Hwy 75 Bridge and Embankment Stabilization Project
SP 6012-57 Letting April 22, 2026
Purpose
To stabilize the bridge and roadway on US 75 north of the town of Climax to allow the roadway to be re-opened as soon as possible while providing a permanent solution to the soil deformation.
Procurement schedule
- Request for Letters of Interest - Dec. 16, 2025
- Request for Qualifications - Dec. 19, 2025
- RFP: Feb. 4, 2026
- Letting: April 22, 2026
- Construction start: Summer 2026
Information
Oversight
- Design and construction post-letting oversight will utilize consultant contracts