Minnesota Department of Transportation

511 Travel Info

Electric vehicle infrastructure

Electric vehicle infrastructure

National Electric Vehicle Infrastructure Program in Minnesota

The National Electric Vehicle Infrastructure (NEVI) Formula Program provides funds to states to build a convenient, affordable, reliable, and equitable fast charging network for EVs across the United States. Program funds must first be used to install direct current fast chargers (DCFC) along any alternative fuel corridors (AFCs) for EV charging that had been designated by the states. After states complete the AFC build-out, they can use the remaining funds on other roadways within the state. 

NEVI funding round 3a request for proposals

MnDOT has opened the round 3a request for proposals for the NEVI program. This phase of NEVI funds will continue our work to support long-distance travel around the state. There are 74 eligible clusters where stations can be proposed and a total of $41.18 million in obligated funds available. 

Timeline

  • Aug. 26, 2026, 9 a.m.: Application window opened
  • Aug. 26 through Oct. 9, 2026: Questions accepted
  • Sept. 23, 2026, 1- 3 p.m.: Application prep webinar
  • Sept. 29, 2026, 9 -11 a.m.: Post-award grantee expectations webinar
  • Nov. 2, 2026, 4 p.m.: Deadline to submit an application to MnDOT
  • Late December 2026 to January 2027: Round 3a conditional awards announced

Guidance

Questions and answers

Responders who have any questions regarding this RFP must submit questions only via our form by 5 p.m. on Oct. 9, 2026.

No MnDOT personnel are allowed to discuss the RFP before the applications are due. Contact regarding this RFP with any personnel may result in disqualification.

We'll publish questions verbatim as submitted weekly each Tuesday through Oct. 13, 2026, along with our responses. Check back for any addendums to the RFP and any questions that have been answered.

Webinars

Resources

How to apply

Each application can include only one site. You may submit only one application per cluster.

Step 1: Download and review the following documents

We strongly urge you to conduct your due diligence as it relates to the NEVI Formula Program and the federal, state and local laws that apply to this funding.

Step 2: Register for a UEI (also called a SAMS number)
Step 3: Register as a vendor in SWIFT

A Vendor ID is required for processing invoices and payments. The grant applicant must obtain the Vendor ID. MnDOT will establish a contract and process invoices directly with the grant applicant. If the grant applicant already has a Statewide Integrated Financial Tools (SWIFT) Vendor ID, you do not need to register again. Navigate to the Supplier Portal Vendor Registration to register as a vendor.

Step 4: Complete the application documents (from Step 1) as described in the RFP

Each application must include the following (unless marked optional), completed attachments and documents, as described in this RFP and in the format identified:

  • Completed General Technical Application Form - Attachment 3, including all required information (searchable PDF format)
  • Completed Project Site Technical Proposal Form - Attachment 4 (searchable PDF format)
  • Signed Cost Proposal Form - Attachment 5 (XLSX format)
  • Signed letter from the site owner (searchable PDF format)
  • Application attachment (searchable PDF format):
    • Area map
    • Site design and layout
    • EVSE cut sheets
    • Electrical infrastructure diagram and details
    • Resumes of key roles and organizational chart
    • Signed certification documents from Attachment 10
  • Completed Utility Coordination Form - optional (searchable PDF format)
  • Signed Acknowledgement of Federal Form 1273 (searchable PDF format)
Step 5: Submit application

If you are experiencing technical issues while submitting an application, email neviproject.dot@state.mn.us for assistance.

After you apply

  • You'll receive automatic email confirmation.
  • We'll convene a scoring committee to review and score all applications.
  • We intend to make up to 40 awards this round with no more than one award per cluster.
  • We intend to announce conditional awards by Dec. 30, 2026. That date is tentative depending on the volume of applications received. We'll publish updates.

Awards

As of Aug. 6, 2026, there are eight operational locations from round 1 and 2 funding:

  • Burnsville (I-35, exit 88B)
  • North Branch (I-35, exit 47)
  • Stewartville (I-90, exit 209)
  • Moose Lake (I-35, exit 214)
  • Forest Lake (I-35, exit 129)
  • Lake Elmo (I-94, exit 251)
  • Albert Lea (I-35, exit 11)
  • Alexandria (I-94, exit 100)

Other locations are in varying stages of pre-construction and construction. We'll update station status as they come online.

AFC Exit Grantee Location Status Maximum grant reimbursement
I-90 12 Francis Energy Charging 1202 S Kniss Ave, Luverne, MN Awarded Round 2 $873,085.44
I-90 43 Kwik Trip 1755 N Humiston Ave, Worthington, MN Awarded Round 2 $680,535.00
I-90 73 Francis Energy Charging 120 Industrial Parkway, Jackson, MN Awarded Round 2 $923,949.63
I-90 119 Francis Energy Charging 1555 Domes Dr, Blue Earth, MN Awarded Round 2 $862,576.49
I-90 157 Kwik Trip 2611 Bridge Ave, Albert Lea, MN Awarded Round 2 $713,097.00
I-90 179 Kwik Trip 1509 10th Place NE, Austin, MN Awarded Round 2 $650,853.00
I-90 209 Kwik Trip 101 Schumann Dr NW, Stewartville, MN Awarded Round 2 $641,421.00
I-90 233 Love’s Travel Stops & Country Stores 2102 Enterprise Drive, St. Charles, MN Awarded Round 2 $998,648.21
I-35 11 Tesla 820 Happy Trails Ln, Albert Lea, MN Awarded Round 1 $546,512.20
I-35 88 B Francis Energy Charging 14350 Nicollet Ct, Burnsville, MN Awarded Round 1 $828,952.68
I-35 129 Kwik Trip 4868 208th St. N, Forest Lake, MN Awarded Round 1 $662,330.40
I-35 147 Kwik Trip 5435 St. Croix Trail, North Branch, MN Awarded Round 1 $596,035.20
I-35 169 Circle K Stores 715 13th Street SW, Pine City, MN Awarded Round 1 $302,281.92
I-35 214 Kwik Trip 4694 Opportunity Drive, Moose Lake, MN Awarded Round 1 $746,764.20
I-35 249 Circle K Stores 9314 W. Skyline Parkway, Proctor, MN Awarded Round 1 $497,735.52
I-94 2B Circle K Stores 3475 28th Avenue S., Moorhead, MN Awarded Round 1 $497,735.52
I-94 22 Energy Hunters 619 Front St N, Barnesville, MN Awarded Round 2 $519,938.50
I-94 54 Francis Energy Charging 610 Western Ave, Fergus Falls, MN Awarded Round 2 $858,540.02
I-94 100 Pilot Travel Centers 3181 Evergreen Lane, Alexandria, MN Awarded Round 1 $783,554.40
I-94 127 Circle K Stores 1185 S Main, Sauk Centre, MN Awarded Round 1 $497,735.52
I-94 164 Love’s Travel Stops & Country Stores 8708 Crossing Drive, Rockville, MN Awarded Round 2 $724,556.60
I-94 205 Kwik Trip 4400 O Day Ave NE, St. Michael, MN Awarded Round 1 $660,662.30
I-94 30 Francis Energy Charging 7011 Northland Cir N, Brooklyn Park, MN Awarded Round 1 $758,677.88
I-94 251 Kwik Trip 8513 5TH ST N, Lake Elmo, MN Awarded Round 2 $649,755.00

What we've done so far

We developed the initial Minnesota Electric Vehicle Infrastructure Plan in 2022 to guide the use of the NEVI formula funds that Minnesota was to receive over FFY 2022-2026. 

We have issued two rounds of Request for Proposals (RFPs) to fund EV charging infrastructure along the state’s three AFCs: I-94, I-90 and I-35. Twenty-four locations are in the process of pre-construction, construction and operations.  

July 2025

We completed an EV Infrastructure Needs Assessment (EVINA) report and the Long-Distance Charging Analysis Dashboard to provide information on EV adoption, EV charging infrastructure needs and potential locations for building charging along long-distance travel corridors.  

September 2025

We submitted a NEVI plan update to FHWA that provides a high-level timeline and actions for MnDOT to take to make use of approximately $41.8 million in FY 2023-2025 NEVI formula funds.

December 2025

We submitted a request to FHWA to certify the Minnesota Alternative Fuel Corridors as fully built out for EV charging. Minnesota FHWA Division approved MnDOT’s request for fully built out certification of our Alternative Fuel Corridors (AFCs) for EV charging. This approval allows MnDOT to move forward with using NEVI funds on other roadways.

February - April 2026

We issued a Request for Information (RFI) to gather insights, ideas, and capabilities from qualified vendors and stakeholders with an interest in supporting the installation and operation of DC fast charging stations along long-distance travel corridors. The RFI was not a solicitation for bids or proposals, but rather an opportunity: 

  • Understand the current market landscape and available solutions
  • Identify potential partners and innovative approaches
  • Inform the development of future Request for Proposals or procurement strategies
  • Clarify technical, operational or financial considerations relevant to our goals
May - August 2026

We took the feedback from the RFI and what we've learned from the first two rounds of grants to update the Request for Proposal process. We held informational meetings and webinars to share our plans for the next RFP.

We worked with grantees from rounds 1 and 2 to move projects through construction to operations