Join us for a public meeting on Wed, March 12 to learn more about the anticipated schedule and what to expect in 2025, including lane closures on Hwy 169 and local detours. For more information, visit the meetings webpage.
About this project
![Intersection of Hwy 169 and Hwy 282/Co. Rd. 9 in Jordan project location map](images/projectmap.png)
Hwy 169 and Hwy 282 in Jordan project location map
We are partnering with the city of Jordan and Scott County on a project which will include a new Hwy 169 and Hwy 282/Co. Rd. 9 interchange, two bridges (over Hwy 169 and railroad tracks), two roundabouts, pedestrian tunnel, sidewalks, retaining walls, and noise walls.
Summary of work
- Construct new interchange at Hwy 169 and Hwy 282/Co. Rd. 9
- Build roundabout at the Co. Rd. 9 and Syndicate St. intersection
- Build roundabout at the Co. Rd. 9 and 190th St./Valley View Dr. intersection
- Build Co. Rd. 9 bridge over Union Pacific railroad tracks
- Widen and repair Hwy 169 bridge over Sand Creek
- Add traffic signal at NB Hwy 169 exit ramp and Hwy 282
- Build pedestrian tunnel under Hwy 169 and add new trail connections
- Construct Hwy 169 acceleration and deceleration lanes
- Build stormwater improvements
- Create retaining walls along various areas of the project
- Add noise walls on both sides of Hwy 169, north of Syndicate St. and Creek Lane
Traffic impacts
All traffic impacts are tentative and weather dependent.
Upcoming
Information about upcoming traffic impacts will be posted as details become available. Motorists can anticipate Hwy 169 lane closures with head-to-head traffic.
Project timeline
The following tentative traffic impacts are anticipated and subject to change:
![Intersection of Hwy 169 and Hwy 282/Co. Rd. 9 in Jordan project staging map](images/stagingmap.png)
Hwy 169 and Hwy 282 in Jordan project staging map
Stage 1: Spring to early summer 2025
- Work begins on Hwy 169 interchange
- Single-lane Hwy 169 traffic in each direction
Stage 2: Summer to fall 2025
- Single-lane Hwy 169 traffic in each direction
- Roundabout construction at Co. Rd. 9 and Valley View Dr.
- Co. Rd. 9 remains open
- Alternating detour for 190th St./Valley View Dr.
- Construct pedestrian underpass
Stage 3: 2026
- Work on Hwy 282/Co. Rd. 9 overpass
- Single-lane Hwy 169 traffic in each direction
- Occasional overnight closures of Hwy 169 for bridge work
- Temporary traffic light at Hwy 169 and Creek Ln.
- Truck traffic exiting and entering Hwy 169 at Co. Rd. 9 will instead be detoured to Delaware Ave./Co. Rd. 59
Stage 4: 2027
- Median and finishing work on Hwy 169
- Single-lane Hwy 169 traffic in each direction
- Remove temporary traffic light at Hwy 169 and Creek Ln.
- Hwy 282/Co. Rd. 9 overpass opens to traffic