Traffic impacts

I-94 between Hwy 120/Century Avenue and the St. Croix River project area map.

I-94 Oakdale to Lakeland project area map

View full-size map

All traffic impacts are tentative and weather-dependent.

Current

Lane closures

Through late October
  • EB I-94 is reduced to three lanes between Century Ave. and Woodbury Dr.
    • Traffic going east past the Woodbury Dr./Keats Ave. N. exit should use the left two lanes
    • Traffic exiting onto I-494, I-694, Radio Dr./Inwood Ave. N. or Woodbury Dr./Keats Ave. N. should use the right lane
  • WB I-94 is reduced to two lanes between Woodbury Dr. and Century Ave.

Ramp closures

7 p.m. Wed, Sept. 18 through mid-October
Through October

Upcoming

Information about upcoming traffic impacts will be posted as details become available.

Ramp closures

5 a.m. Thu, Sept. 26 through mid-October
  • The ramps to/from EB I-94 and Woodbury Dr./Keats Ave. N. are closed
    • EB I-94 and Woodbury Dr./Keats Ave. N. detour: EB I-94, Manning Ave., WB I-94 and Woodbury Dr./Keats Ave. N.
    • Woodbury Dr./Keats Ave. N. to EB I-94 detour: Woodbury Dr./Keats Ave. N., WB I-94, Radio Dr./Inwood Ave. N. and EB I-94

About this project

A large pavement project on I-94 between Century Ave. and the St. Croix River will begin in July 2022. This project work is anticipated to take two and a half years to complete.

Summary of work

  • Resurface pavement and ramps
  • Construct new eastbound lane from I-494 to Woodbury Dr.
  • Resurface frontage road (Hudson Rd.) in the project area
  • Upgrade pedestrian/bicycle accessibility
  • Repair drainage
  • Replace signage
  • Upgrade lighting
  • Install median barrier