Washingston St.—Brainerd

Hwy 210 from Baxter Dr. to Pine Shores Rd.,Crow Wing County

Reconstruct, improve

MnDOT will reconstruct and improve Washington St. (Hwy 210) through Brainerd from Baxter Dr. to
Pine Shores Rd. in 2026 and 2027.

Summary of work

Hwy 210

  • Reconstruct (bridge, central, mall/railyard segments) or resurface (west and east segments) the road
  • Reconstruct curbs, gutters, raised medians and storm sewers
  • Update signal systems
  • Remove signal systems at 4th Ave. NE and Mill Ave.
  • Realign and improve access at the Hwy 210 and Hwy 25/Mill Ave., includes two roundabouts
  • Upgrade city utilities beneath the road
  • Upgrade pedestrian sidewalks and approaches and reconstruct/connect the Cuyuna Lakes Trail
  • Update the Mississippi River Bridge
Project location map and general segments. Select image to enlarge

Hwy 210 segments

  • West — Baxter Dr. to 4th St.
  • Bridge — 4th St. NW to east of the Mississippi River at E River St./N 1st St.
  • Downtown — E River St./N 1st St. to west of 13th St. SE
  • Mall/Railyard — east of Kingwood St. to east of 10th Ave. NE
  • East — 10th Ave. NE to Pine Shores Rd.

Work segments subject to change once more is known.

Future impacts

Hwy 210 in Brainerd
Hwy 210 Brainerd westward towards Baxter. Photo by the City of Brainerd.

Motorists: One-lane traffic, changes to access along Hwy 210, gravel surfaces, segments of detours

Pedestrians: Sidewalk closures, signed detours

More details to become available closer to construction