Off-road work and shoulder closures to occur year-round
Hwy 24
Primary work in 2026 is to widen and prepare work areas for 2027.
Open in both directions through Clearwater
Expect narrow lanes with no shoulders, reduced speeds, lane shifts and slow moving vehicles entering and exiting work areas, flaggers and stop-and-go traffic
Access may change at times, follow signs
Note: Wright County roundabout construction at Co. Rd. 7
Access to businesses open and maintained
I-94
Open in both directions at Hwy 24 in Clearwater
Expect narrow lanes/no shoulders, lane shifts and reduced speeds. Crews at work along the interstate
Single-lane closures at off-peak times
Exit/entrance ramps open
Reconstruct interchange
MnDOT will reconstruct and improve the Hwy 24 interchange at I-94 in Clearwater, Wright County. This includes roundabouts and a new bridge in 2026-2027.
The project will begin in mid-summer 2026 and take two years to complete.
Expect impacts in these work areas along Hwy 24 in Clearwater. MnDOT Hwy 24 and I-94 interchange area; Wright County work on Hwy 24 at Co. Rd. 7 Select work zone map image to enlarge (PNG)
Schedule at a glance
All traffic impacts are tentative and subject to change. Off-road work to occur year-round
Times
Work
Impacts
Fall 2025-summer 2026
Prepare work areas
Shoulder closures, periodic lane closures, crews working along areas
Mid-summer-fall 2026
Work mainly along Hwy 24:
Construct new bridge southeast of current structure
Widen areas along the road, construct temporary connections for 2027 work
Lane or shoulder closures, narrow lanes and/or lane shifts in the Hwy 24 work zone
Some Hwy 24 overnight closures at I-94 with detour (Google) to complete bridge work: place steel girders, pour the concrete deck
Hwy 24 detour uses Co. Rd. 75 Clearwater, Co. Rd. 8 Hasty and Co. Rd. 39 back to Hwy 24 north of Annandale
Changes to access
Reduced speeds
Spring-fall 2027
Reconstruct road, connections:
Road surface, medians, on-off ramps, roundabouts, side street approaches, multi-use trail, storm drainage structures, road markings and sign, turf and any other necessary repairs
Remove old bridge
Construct under traffic:
Lane or shoulder closures, narrow lanes and/or lane shifts in the Hwy 24 work zone
Changes to access and use of temporary or alternate entrances or exits
Reduced speeds
Hwy 24 at Co. Rd. 7
Wright County will construct a new roundabout on Hwy 24 and Co. Rd. 7 in Clearwater in 2026. Estimated cost $6 million
Tentative impacts:
Hwy 24: Narrow lanes with no shoulders while the roundabout is built