About this project
Update
Hwy 76 motorists near Money Creek will again be able to use both lanes of the bridge at mile post 27.96 as the lane was reopened on Oct. 13 and the temporary traffic signals were removed which were used during construction work.
On Oct. 7, the detour was removed on Hwy 76 between I-90 and Houston after MnDOT completed repairs of the other bridge at mile post 26.34 which is also part of this project.
Motorists are reminded to slow down as they approach the bridges and will see signs warning of a bump as they travel onto the bridges. Paving work where the road meets the bridges is scheduled in the weeks ahead, so a bump is present on both bridges.
Summary of work
In 2022, crews will repair two bridges on Hwy 76 over Money Creek, north of Houston. This includes resurfacing the concrete bridge deck. Construction is scheduled from Sept. 6 to October.