About this project

View full-size map
We are making significant improvements to Hwy 280 from I-94 in St. Paul to Hwy 36/I-35W in Roseville.
In 2026 we will resurface Hwy 280 from I-94 to Hwy 36/I-35W, repair bridges, repair and resurface ramps, repair drainage and make additional improvements. Resurfacing of aging pavement on Hwy 280 will provide a smoother ride for motorists and extend the life of the existing highway.
In 2028, we will make safety and accessibility improvements for those that travel along and across Hwy 280. These improvements are still being analyzed and considered. We will also permanently close the left turn from Hwy 280 to Broadway St. N.E.
Summary of work
2026
- Resurface Hwy 280 from I-94 to Hwy 36/I-35W
- Repair Hwy 280 bridges over the following locations:
- I-94
- University of Minnesota Transitway and railroad tracks
- Energy Park Dr.
- Como Ave.
- Hennepin/Larpenteur Ave.
- I-35W
- Repair and resurface the following ramps:
- Energy Park Dr.
- Como Ave.
- Larpenteur Ave.
- St. Croix St.
- Repair drainage
- Install new traffic signs
- Replace guardrails
2028
- Upgrade sidewalks to meet ADA requirements
- Install new traffic signals at Franklin Ave. and Territorial Rd.
- Repair bridges that carry traffic over Hwy 280 at the following locations:
- Wabash Ave.
- Franklin Ave.
- University Ave.
- Territorial Rd.
- Additional safety and accessibility improvements to streets along and across Hwy 280 are still being analyzed and considered