Route (Hwy or Interstate) |
Description |
Begin date |
End date |
Total cost |
2025 construction cost |
Website |
Hwy 14 |
Resurface Hwy 14 from Hwy 52 to CR 36 (Marion Road) in Rochester |
June 2025 |
August 2025 |
$4 million |
$4 million |
mndot.gov/d6/projects/hwy14-resurfacing |
Hwy 14 |
Improve drainage and slope stabilization on Stockton Hill between Stockton and Winona |
June 2025 |
November 2025 |
$7.38 million |
$7.38 million |
mndot.gov/d6/projects/hwy14-stockton-winona |
Hwy 19 |
Construct roundabout at Hwy 19 and CR 2 near Lonsdale |
July 2025 |
November 2025 |
$2.6 million |
$2.6 million |
mndot.gov/d6/projects/hwy-19-roundabout |
Hwy 52 |
Resurface Hwy 52 northbound lanes north of Zumbrota and Hwy 60 to north of CR 7 |
September 2025 |
October 2025 |
$2.5 million |
$2.5 million |
None |
Hwy 57 |
Resurface Hwy 57 from 16th St in Kasson to the Zumbro River in Mantorville |
September 2025 |
October 2025 |
$400,000 |
$400,000 |
None |
Hwy 60 |
Replace signals and make intersection improvements on Hwy 60 in Faribault at Western Ave and 3rd St NE (year 2 of 2) |
July 2024 |
July 2025 |
$2.5 million |
$1.8 million |
mndot.gov/d6/projects/traffic-signal-replacement |
Hwy 63 |
Construct roundabout at Hwy 63 and CR 112 north of Rochester |
June 2025 |
August 2025 |
$3.8 million |
$3.8 million |
talk.dot.state.mn.us/hwy63-cr112 |
I-90 |
Replace westbound I-90 bridge over Cedar River, repair westbound I-90 bridge over 6th St NE, replace bridge CR 45 (4th St NW) over I-90 in Austin (year 2 of 3) |
April 2024 |
November 2026 |
$49.9 million |
$25 million |
mndot.gov/d6/projects/i90-austin-bridge-replacements |
I-90 |
Resurface I-90 westbound lanes from Hwy 16 at Dexter to 28th St NW in Austin |
May 2025 |
August 2025 |
$7.8 million |
$7.8 million |
mndot.gov/d6/projects/I-90-austin-dexter |
I-90, Hwy 52 |
Replace I-90 bridges, construct new ramp/bridge over Hwy 52, replace box culverts and reconstruct ramps southeast of Rochester (year 2 of 3) |
July 2024 |
November 2026 |
$27.37 million |
$13 million |
mndot.gov/d6/projects/i90-hwy52 |
Hwy 246 |
Resurface Hwy 246 from CR 26 at Nerstrand to Hwy 56 |
July 2025 |
October 2025 |
$3.2 million |
$3.2 million |
mndot.gov/d6/projects/hwy246 |