This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.
Traffic impacts

I-94 in Minneapolis project area map
All traffic impacts are tentative and weather dependent.
Current
Lane closures
5 a.m. Mon, June 16 through early August
- Cedar Ave. is reduced to one lane in each direction under the I-94 bridges
5 a.m. Mon, April 7 through mid-August
- I-94 is reduced to two lanes in both directions between 11th Ave. South and Franklin Ave. Southeast
5 a.m. Mon, March 31 through mid-August
- The following ramps are reduced to one lane:
- Southbound I-35W to eastbound Hwy 55
- Westbound Hwy 55 to South 7th St.
Ramp closures
9 p.m. Fri, June 13 through mid-August
- The following ramps are closed:
- Northbound I-35W to eastbound I-94
- Huron Blvd. to eastbound I-94
- Eastbound I-94 to Huron Blvd.
- South 6th St. to eastbound I-94
- Riverside Ave. to eastbound I-94
- Cedar Ave. to eastbound I-94
Trail closure
5 a.m. Mon, June 16 through mid-July
- Hiawatha LRT Trail is closed between 15th Ave. South and East Franklin Ave.
- Pedestrian detour: Cedar Ave. (PNG)
- Bicyclist detour: 20th Ave. South and South 6th St. (PNG)
Upcoming
Information about upcoming traffic impacts will be posted as details become available. Motorists can expect lane and ramp closures during construction. Motorists should be aware that some nearby construction projects will have overlapping traffic impacts with the I-94 Minneapolis work. All lanes on I-94 between 11th Ave. South and Franklin Ave. Southeast are expected to reopen to traffic for the Minnesota State Fair from mid-August through Labor Day. Work will resume after Labor Day to complete the removal of crossovers and other items such as signage and lighting.
Bridge closures
Mid-July through early August
- Riverside Ave. bridge over I-94 is closed
- Motorist and bicyclists detour: East Franklin Ave., 26th Ave. South and 25th Ave. South (PNG)
- Pedestrian detour: South 9th St. and 25th Ave. South (PNG)
About this project
We will be doing maintenance and repair work on five bridges along I-94 in Minneapolis. These bridges include:
- I-94 bridge (Dartmouth Bridge) that spans the Mississippi River
- Riverside Ave. bridge over I-94
- I-94 over Cedar Ave.
- I-94 over the Light Rail Transit (Blue Line)
- I-94 over Hwy 55/Hiawatha Ave.
Summary of work
- Construct temporary crossovers
- Repair bridge decks
- Resurface bridge pavement
- Remove and replace bridge joints
- Update guardrails
- Upgrade drainage
- Repaint bridge steel