Minnesota Department of Transportation

511 Travel Info

Project selection

Increasing the transparency of how we select highway construction projects

Urban non-freeway/non-expressway pavement projects

MnDOT District 3

Scoring criteria for urban non-freeway, non-expressway pavement projects. Out of 100 possible points, 25 points are based on the timing of the improvement, 25 points are based on cracking, rutting and patching, 10 points are based on traffic volume, 10 points are based on compliance with the Americans with Disability Act, 10 points are based on active transportation and transit, 10 points are based on other infrastructure needs, 5 points are based on the condition of local utilities under the road, and 5 points are based on whether the project will benefit an environmental justice population.

Learn more about how MnDOT evaluates and selects urban pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. MnDOT scores and prioritizes urban non-freeway/non-expressway pavement projects separately from the normal pavement scoring process, because of their complexity, utilities and other infrastructure and level of required local coordination and public involvement. In many instances, these roads function both as state highways and as city streets. These pavement projects can be on either National Highway System or non-NHS.

Freeways have full access control (no driveways, signals or at-grade intersections). Expressways have partial access control (limited or no driveways, few and widely spaced intersections, and may include some grade separated crossings). Both are high speed roads designed to facilitate longer trips.

For the purposes of this scoring category, MnDOT uses a flexible, context-based definition of urban. This includes areas with medium-to-high density adjacent development with small to medium setbacks, and in some instances no setback. This includes both residential, industrial and commercial areas. In some instances, the urban context may cover less than a quarter mile.

Urban pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related Links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2024

Score Route  Community Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
83 MN210 Aitkin Hwy 210 from Hwy 169 to to the Ripple River Bridge $15,723,000 2032 0118-23
70 MN15 Saint Cloud/Sauk Rapids Resurface MN 15 from Stearns CSAH 47 in St Augusta to Benton CSAH 33 Entrance Ramp in Sauk Rapids $21,100,000 2033 7303-1073903
65 US169 Aitkin Hwy 169 from Westwood Dr to the South Junction of Hwy 210 $4,166,000 2032 0115-56
53 MN84 Pine River Resurface MN 84 from Jct MN 371 to 5th St in Pine River or reconstruct $1,200,000 2033 1110-1090924
53 MN95 Cambridge From Fern St to Fillmore St in Cambridge $17,100,000 2026 3006-39
50 MN55 Annandale From Poplar Ave to 0.25 miles east of Annandale Blvd in Annandale $10,300,000 2025 8606-63
25 MN210 Baxter From 0.26 Mi W of Timberwood Dr to Baxter Dr in Baxter $5,903,000 2025 1805-81
25 MN27 Wahkon Reconstruction MN 27 from 0.1 Mi W of 1st St to 200 feet E of 3rd St in Wahkon; $2,821,154 2026 4804-23
24 MN22 Eden Valley Thin mill and overlay from MN55 to Hutchenson Ave  $240,000 Not Selected

 

Previous years

Score Route  Community Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
83 MN210 Aitkin Hwy 210 from Hwy 169 to to the Ripple River Bridge $5,727,000 2032 0118-23
70 MN15 Saint Cloud/Sauk Rapids Resurface MN 15 from Stearns CSAH 47 in St Augusta to Benton CSAH 33 Entrance Ramp in Sauk Rapids $12,000,000 2032 7303-1073903
65 US169 Aitkin Hwy 169 from Westwood Dr to the South Junction of Hwy 210 $4,166,000 2032 0115-56
53 MN84 Pine River Resurface MN 84 from Jct MN 371 to 5th St in Pine River or reconstruct $2,000,000 2032 1110-1090924
53 MN95 Cambridge From Fern St to Fillmore St in Cambridge $10,100,000 2026 3006-39
50 MN55 Annandale From Poplar Ave to 0.25 miles east of Annandale Blvd in Annandale $11,900,000 2025 8606-63
35 MN23 St. Cloud Reconstruction from 4th Ave S to Benton County Road 1  $33,400,000 There is a segment of TH10 associated w/this project
25 MN210 Baxter From 0.26 Mi W of Timberwood Dr to Baxter Dr in Baxter $4,500,000 2025 1805-81
25 MN27 Reconstruction MN 27 from 0.1 Mi W of 1st St to 200 feet E of 3rd St in Wahkon; $2,100,000 2026 4804-23
24 MN22 Eden Valley Thin mill and overlay from MN55 to Hutchenson Ave  $240,000 Not Selected

Score Route  Community Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
83 MN210 Aitkin Hwy 210 from Hwy 169 to to the Ripple River Bridge $5,300,000 2030 0118-23
70 MN15 Saint Cloud/Sauk Rapids Resurface MN 15 from Stearns CSAH 47 in St Augusta to Benton CSAH 33 Entrance Ramp in Sauk Rapids $12,500,000 2032 7303-1073903
65 US169 Aitkin Hwy 169 from Westwood Dr to the South Junction of Hwy 210 $3,856,000 2030 0115-56
60 US71 Menahga Medium mill and overlay from 3rd St SE to MN87  $7,700,000 Not Selected Cost includes rural mill and overlay
53 MN84 Pine River Resurface MN 84 from Jct MN 371 to 5th St in Pine River or reconstruct $500,000 2031 1110-1090924
53 MN95 Cambridge From Fern St to Fillmore St in Cambridge $12,000,000 2026 3006-39
50 MN55 Annandale From Poplar Ave to 0.25 miles east of Annandale Blvd in Annandale $8,050,000 2025 8606-63
45 US12 Delano Medium mill and overlay from 72nd St to Wright/Hennepin County Line  $2,700,000 Not Selected
43 MN25 Buffalo Reconstruct MN 25, from 0.2 mile north of Settlers Parkway to 1st St S in Buffalo. $10,863,055 2023 8604-37
25 MN210 Baxter From 0.26 Mi W of Timberwood Dr to Baxter Dr in Baxter $4,500,000 2025 1805-81
25 MN27 Reconstruction MN 27 from 0.1 Mi W of 1st St to 200 feet E of 3rd St in Wahkon; $2,100,000 2026 4804-23
24 MN22 Eden Valley Thin mill and overlay from MN55 to Hutchenson Ave  $240,000 Not Selected

Score Route  Community Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
75 US169 Aitkin Reconstruction from Westwood Rd to MN210  $6,020,000 2031 D1 Funding
70 MN23 Waite Park Medium mill and overlay from 10th Ave to MN15  $9,920,000 2026 Cost includes part of a rural mill and overlay
70 MN15 St. Cloud Medium mill and overlay from MN23 to County Road 33  $12,000,000 2031 The project cost is part of a larger rural mill and overlay.
65 MN25 Monticello/Big Lake Medium mill and overlay from I94 to US10  $4,740,000 2030 Cost includes rural portion
65 MN210 Aitkin Reconstruction from US169 to Ripple River Bridge   $6,180,000 2031 D1 Funding
62 US169 Vineland Medium mill and overlay from Vineland to Ojibwe Dr  $12,890,000 2031 Cost includes rural mill and overlay
62 MN210 Deerwood Medium mill and overlay from 1000 ft from MN6 to .4 miles east of MN6 in Deerwood  $2,630,000 2027 Costs include rural mill and overlay
60 US10 Big Lake Reconstruction from MN25 to Eagle Lake Rd  $7,808,000 2029  
60 MN23 St. Cloud Medium mill and overlay from MN 15 to 4th av S  $5,530,000 2029  
60 MN65 Mora Reconstruction from .8 miles north of MN23 to .4 miles north of MN23  $4,490,000 2029 Project cost includes rural portion
60 US71 Menahga Medium mill and overlay from 3rd St SE to MN87  $7,700,000 2027 Cost includes rural mill and overlay
60 MN210 Brainerd Reconstruction from Baxter Dr to 1.6 miles east of MN25  $23,000,000 2025  
58 MN23 Milaca Reconstruction from south end of bridge 48030 to 105th Ave  $12,100,000 2026  
58 MN25 Buffalo Reclaim and overlay from 14th St to 1.6 miles north of MN55  $8,100,000 2026 Cost is part of a larger rural reclaim project
57 MN371 Baxter Reclaim and overlay from MN 210 to Crow Wing County Road 77/49  $15,650,000 2030 Project cost includes rural portion
55 US71 Long Prairie Reconstruction from 230th to Todd County Road 56  $11,190,000 2030 Project cost includes rural portion
55 US169 Garrison Reconstruction from Garrision to Pike Road  $5,000,000 2025  
54 MN25 Pierz Medium mill and overlay from MN27 to 4th Ave N  $580,000 Not Selected New Project
53 MN95 Cambridge Reconstruction from Fern St to Davis St  $12,000,000 2025  
53 MN84 Pine River Thick mill and overlay from MN371 to Pine River  $500,000 2031
52 MN23 Foley Medium mill and overlay from MN25 to .5 miles east of MN25  $100,000 2030  
52 MN87 Backus Medium mill and overlay from C&G in Backus to MN371  $90,000 Not Selected New Project
50 US10 St. Cloud Reconstruction from Railroad crossing to 15th Ave  $33,700,000 2023 There is a segment of TH23 associated w/this project.
50 MN55 Buffalo Medium mill and overlay from MN25 to Wright County Road 134  $4,350,000 2028  
49 MN27 Little Falls Medium mill and overlay from 9th St NE to US 10  $1,110,000 2027  
49 US71 Wadena Full mill and replace from Franklin Ave to Elm Ave  $7,300,000 2025  
48 MN6 Remer Reconstruction from west of MN200 to east of MN  $2,100,000 2022  
47 MN238 Upsala Medium mill and overlay from Walnut Ave to 3rd Ave  $1,420,000 2029  
45 US12 Delano Medium mill and overlay from 72nd St to Wright/Hennepin County Line  $2,700,000 2027  
45 US71 Sauk Centre Reconstruction from I94 to 4th St N  $11,300,000 2026  
44 US10 Motley Medium mill and overlay from Todd County line to Long Prairie River  $2,700,000 2028  
44 MN371 Pine River Medium mill and overlay from Norway Brook to Cass County Road 2  $4,330,000 2027 Project cost includes rural portion
44 MN107 Braham Reconstruction within Braham city limits  $3,000,000 2027 Cost includes rural mill and overlay
43 MN25 Buffalo Reconstruction from Bradshaw Ave to 1st St  $2,420,000 2023  
35 MN23 St. Cloud Reconstruction from 4th Ave S to Benton County Road 1  $33,400,000 2023 There is a segment of TH10 associated w/this project
28 MN55 Annandale Reconstruction from Wright County Road 5 to reference point 143  $5,100,000 2023  
25 MN25 Buffalo Thin mill and overlay from 1st St to 14th St  $770,000 2030  
25 MN241 St. Michael Minor CPR and diamond grinding with overlay from Wright County Road 19 to I94  $2,030,000 2030  
24 US10 Staples Medium mill and overlay from Staples City limits to 1st Ave BE  $2,900,000 2027  
24 MN22 Eden Valley Thin mill and overlay from MN55 to Hutchenson Ave  $240,000 Not Selected New Project
22 MN210 Aitkin Unbonded overlay from Ripple River Bridge to Aitkin County Road 81/12  $20,000,000 2022  
19 MN287 Long Prairie Thin mill and overlay from 9th St to US71  $970,000 2025  
9 MN23 Foley Reconstruction from MN25 to Benton County Road 15  $15,000,000 2022 Cost includes rural mill and overlay

 

Score Route  Community Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
85 US 71 Wadena Reconstruction from Franklin Ave to Elm Ave in Wade a $5,100,000 2025  
80 MN 371 Walker Reconstruction from Highland Dr to Hwy 34 in Walker $7,000,000 2027  
75 US 10 Elk River Mill and overlay from Norfolk/Elk River to Main st in Elk River $400,000 Not Selected  Not  district priority. Will continue to monitor pavement performance.
75 MN 25 Buffalo Reconstruction from Bradshaw Ave to 1st St in Buffalo $1,300,000 2023  
73 MN 25 Monticello Reconstruction from 7th St left turn to Hwy12/Nelson Blvd in Monticello $1,500,000 Not Selected  Not  district priority. Will continue to monitor pavement performance.
67 MN 65 Mora Reconstruction from Ann River to Hwy 23 in Mora $5,700,000 2029  
65 MN 23 St. Cloud Mill and overlay from Stearns County Road 15 to West of 4th Ave in Saint Cloud $1,700,000 2027  
63 MN 84 Pine River Reconstruction from Hwy 371 to east of Pine River Bridge in Pine River $2,300,000 Not Selected  Not  district priority. Will continue to monitor pavement performance.
62 US 71 Long Prairie Reconstruction from 230th St to Todd County Road 56 in Long Prairie $7,900,000 2030  
60 MN 25 Monticello Thin mill and overlay from 4 lane section to I-94 Bridge in Monticello $1,000,000 Not Selected  Not  district priority. Will continue to monitor pavement performance.
60 MN 27 Little Falls Mill and overlay from 9th St NE to 19th St in Little Falls $1,200,000 2027  
60 US 169 Vineland Mill and overlay from 4 lane section to Ojibwe Dr in Vineland $1,100,000 Not Selected  Not  district priority. Will continue to monitor pavement performance.
58 MN 25 Pierz Mill and overlay from Hwy 27 to 4th Ave in Pierz $300,000 Not Selected  Not  district priority. Will continue to monitor pavement performance.
58 MN 55 Annandale Mill and overlay from County Road 5 to Hwy 24 in Annandale $200,000 2022 Selected prior to policy (in 2019-2022 STIP)
55 MN 95 Cambridge Reconstruction from Fern st to Davis St in Cambridge $9,000,000 2024 Selected prior to policy (in 2019-2029 CHIP)
55 MN 210 Brainerd Thin mill and overlay from Baxter City limits to 3rd St NW in Brainerd $2,500,000 2024 Selected prior to policy (in 2019-2029 CHIP)
54 US 71 Sauk Centre Reconstruction from North end of bridge over I-94 to 4th St in Sauk Centre $13,700,000 2025 Selected prior to policy (in 2019-2029 CHIP)
53 MN 210 Aitkin Mill and overlay from Hwy169 to Ripple River Bridge in Aitkin $4,300,000 2028 Selected prior to policy (in 2019-2029 CHIP)
50 MN 23 St. Cloud Reconstruction from 4th Ave to Benton County Road 1 in Saint Cloud $8,600,000 2024 Selected prior to policy (in 2019-2029 CHIP)
48 MN 6 Remer Mill and overlay from West to East Jct of Hwy 200 in Remer $200,000 2022 Selected prior to policy (in 2019-2022 STIP)
48 US 169 Garrison Reconstruction from Division to Pike Rd in Garrison $4,000,000 2025 Selected prior to policy (in 2019-2029 CHIP)
45 US 10 Elk River Mill and overlay from 185th ave to Norfolk/Elk River City Limits $1,900,000 2021 Selected prior to policy (in 2019-2022 STIP)
45 US 10 Big Lake Mill and overlay from Hwy 25 to 185th Ave in Big Lake $12,800,000 2028 Selected prior to policy (in 2019-2029 CHIP)
44 MN 210 Crosby Reconstruction from 6th Ave to East end of Hospital Parking Lot $4,700,000 2021 Selected prior to policy (in 2019-2022 STIP)
43 MN 238 Albany Diamond Grinding from I-94 to Stearns County Road 10 in Albany $100,000 Not Selected   
40 MN 371 Hackensack Reconstruction from Cass County Road 40 to Cass County Road 5 in Hackensack  $4,000,000 2025 Selected prior to policy (in 2019-2029 CHIP)
39 US 10 Staples Mill and overlay from West Limits of Staples to 1st Ave NW $2,900,000 2027 Selected prior to policy (in 2019-2029 CHIP)
35 US 12 Delano Mill and overlay from 72nd St to Wright/Hennepin County Line in Delano $2,900,000 2027 Selected prior to policy (in 2019-2029 CHIP)
30 US 10 Long Prairie Mill and overlay from Todd County Line to north of Long Prairie River $3,200,000 2025 Selected prior to policy (in 2019-2029 CHIP)
29 MN 29 Wadena Mill and overlay from .4 miles south of Hwy 71 to Hwy 71 in Wadena $800,000 2025 Selected prior to policy (in 2019-2029 CHIP)
28 MN 23 Milaca Reconstruction from Bridge 48030 to 105th Ave in Milaca $9,400,000 2025 Selected prior to policy (in 2019-2029 CHIP)
27 US 12 Cokato Minor Rehabilitation from Meeker/Wright County Line to W Cokato City limits $400,000 2027 Selected prior to policy (in 2019-2029 CHIP). Segment funded by D8
27 MN 287 Long Prairie Mill and overlay from 9th St to Hwy71 in Long Prairie $900,000 2025 Selected prior to policy (in 2019-2029 CHIP)
24 MN 27 Long Prairie Chip seal from Hwy 71 to 9th St NE in Long Prairie $200,000 Not Selected   
23 MN 22 Eden Valley Chip seal from Meeker/Stearns County Line to Hutchenson Ave in Eden Valley $200,000 Not Selected   
22 MN 6 Emily Thin mill and overlay from .25 miles south of Crow Wing County Road 1 to .4 miles south of County Road 1 in Emily $200,000 Not Selected   
21 MN 4 Lake Henry Thin mill and overlay from Stearns County Road 19 to Cartway Drive near Lake Henry  $100,000 Not Selected   
20 MN 25 Buffalo Thin mill and overlay from 1st st to 14th St in Buffalo $1,100,000 2030 Conditions on the ground are expected to deteriorate faster than the model predicts
12 US 71 Elrosa Chip seal from southern limits of Elrosa to northern City limits $200,000 Not Selected   
45 MN 27 Mille Lacs Reconstruction from 1st st to 3rd St in Wahkon $2,000,000 2024 Selected prior to policy (in 2019-2029 CHIP)

Score Community Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
84 Wadena US71 Reconstruction from Franklin Ave to Elm Ave $3,500,000 2025  
79 Sauk Centre US71 Reconstruction from I-94 to 4th St $16,000,000 2025  
75 Buffalo MN25 Reconstruction from Bradshaw Ave to 1st St $6,200,000 2023  
75 Elk River US10 Medium mill and overlay from Norfolk to Main St $400,000 Not selected Only westbound segment is considered in poor condition, waiting to program with eastbound section
67 Mora MN65 Reconstruction from 0.8 miles north of Hwy 23 to 0.4 miles north of Hwy 23 $6,800,000 2028  
66 Long Prairie US71 Reconstruction from Long Prairie River Bridge to Todd County Road 56 $5,900,000 Not selected Not a current district priority, but will continue to monitor pavement performance
65 St. Cloud MN23 Medium mill and overlay from Highway 15 to Railroad Bridge near Highway 10 $5,800,000 2028  
65 Brainerd MN210 Thin mill and overlay from Baxter to 3rd St NW $2,500,000 2025  
65 Pine River MN84 Reconstruction from Highway 371 to Pine River Bridge $4,600,000 Not selected Not a current district priority, but will continue to monitor pavement performance
60 Cambridge MN95 Reconstruction from Fern St to Davis St $8,600,000 2024 Selected prior to policy (in 2019-2028 CHIP)
60 Monticello MN25 Medium mill and overlay from Monticello to I-94  $800,000 2029 Coordinated with a larger pavement project on Highway 25
48 Eden Valley MN22 Reconstruction from Meeker/Stearns County line to Hutchenson Ave $3,200,000 Not selected
43 Genola MN25 Thin mill and overlay from Highway 27 to 4th Ave N $400,000 2025 Selected prior to policy (in 2019-2028 CHIP)
35 Little Falls MN27 Thin mill and overlay from 127th Ave to 9th St $1,100,000 Not selected
34 Milaca MN23 Reconstruction from South end of Bridge 48030 to 0.1 mile east of 48030 $5,500,000 2025 Selected prior to policy (in 2019-2028 CHIP)
30 Albany MN238 Minor concrete pavement rehabilitation from Railroad Ave to Stearns County Road 54 $200,000 Not selected
27 Remer MN6 Thin mill and overlay from East Junction of Highway 200 to West Junction Highway 200 $500,000 Not selected
16 Ironton MN210 Thin mill and overlay from 6th Ave to East end of hospital parking lot $1,100,000 Not selected
15 Waukon MN27 Reconstruction from 85th Ave to Hennepin Ave  $1,200,000 2024 Selected prior to policy (in 2019-2028 CHIP)