Base Construction
- Obtain completed Certification of Aggregates and Granular Materials (form G&B-104) from the contractor.
- Prior to placing the base, verify that the subgrade has been constructed to the required grade and cross-section. Subgrade is to be free of ruts, soft spots, large stones, and excess dust.
- Monitor placement operation. Ensure the Contactor has required Compactors for the compacted lift thickness.
- Check depth and yield (ton per station) to ensure uniform coverage.
- Obtain samples for testing (graduation, moisture, compaction compliance., etc.) as required and perform the necessary tests.
- Ensure compaction, test rolling, and cross-section meets requirements before placing next lift.
- Where weight tickets are required; collect, check, and initial them for each load as they arrive at site.
- Maintain records including hours, location, lift thickness, test results, quantity, yield, and other events or information having bearing on work.
References: Specifications 1601, 2211, 2221, 3138, Grading and Base Manual (Section .002), Contract Administration Manual, Schedule for Material Control.